![]() |
Andorra
Grau de
la Sabata - an/12
Highway
TBM
pilot drive for 1.2 km-long bi-directional NATM road tunnel completed at rates
up to 2 m/h by Subterra for FCC using Wirth 4.5 m-diameter TB 390/420E owned
by Murer in Devonian hornfels and shales with two granodiorite sections of UCS
125 Mpa and RMR 50-65. TBM will now mine parallel emergency exit tunnel. Full
report in Tunel
2/2002. Visit www.subterra.cz
and www.wirth-europe.com
28/02.
Australia
Sydney - au/12
Northside Storage Tunnel
TBM
Interceptor sewer and access tunnels,
in total 20km of TBM drive using three Wirth machines of diameters 6.57m, 6.33m
and 3.8m. Access tunnels driven by roadheader. Spoil from North Head excavations
will be transferred to a loading wharf. Small TBM started October 1998 and large
machines early-1999. Completion 2000. Dec 1998.
First breakthrough recorded at Little Manly Point by 3.8 m Wirth after 1.2 km drive in 10 weeks. Advances of 40 m per 10 h shift, and cutter life consistently more than 200 m. Machine upgraded for 7.5 km Lane Cove tunnel starting June, 1999. The second and third Wirth TBMs will commence their drives in July and august, 1999. Northside Storage Alliance comprises Transfield, Montgomery Watson, Connell Wagner and Sydney Water. June 1999.
Connell Wagner reports project will capture sewage from four major overflow points for transfer to North Head STW and discharge through ocean outfall. Ten shafts, 3 km of access tunnels and two underground pumping stations completed. Project now has a fourth TBM, a Robbins remanufactured by Terratec and increased in diameter from 5.5m to 6.5 m. This is a double shield with multiple modifications by Terratec to suit the Sydney sandstones. Due to the tight delivery requested, CTS of Kent, WA, USA assisted with design services.
The
Wirth 3.8 m and 6.56 m TBMs are consistently achieving 250 m/week, and all three
are now on 2 x 12 h/day operation. The 180 m-high, 650 t/h vertical shaft conveyor
at North Head is the longest in the southern hemisphere, possibly in the world.
Most of spoil removed by barge for reuse inland. December 1999.
Contractor reports final
breakthrough on Sunday, 16th July to complete 20 km of storage tunnel and all
other tunnelling on the project within a two-year span. Total excavation 1.8
million t, or 720,000 cu m, of sandstone and shale, one-third by roadheader
and two-thirds by TBM. Visit www.connellwagner.com
and www.wirth-drilling.com
July 2000.
Australia
Brisbane
- au/15
Transit Bus
Joint venture contractors Peabody and Leighton excavating
400 m-long x 12 m-wide x 7 m-high bus tunnel at Vulture Street using 120 t Paurat
T3.20 roadheader. Work commenced in September, 1999 from the Southbank portal
and in November, 1999 from the Stanley Street portal, with breakthrough anticipated
first quarter 2000. Excavation in stages using canopy tubes, face nails, Ingersoll
Rand Split Set rockbolts, and shotcrete. More from adelaide@sdscorp.com.au
January 2000.
Inner
northern busway section 1 project team comprising Queensland Transport, Halcrow,
Transfield Contractors, Henry Walker Eltin Contractors and GHD Consultants will
undertake 650 m-long, two-lane underground busway in the heart of the city to
link existing bus station to proposed bus station. Tunnel traverses an old riverbed
through a range of materials from soft alluvium to rock using cut-and-cover
and drill/blast. Construction commences this month for completion November,
2001. Visit www.halcrow.com
July 2000.
China
Qinling - cn/26
Xi'an-Ankang
Railway
Completion reported on August 22nd, 1999
of 18 km-long twin tunnels in remote region using drill/blast for one tube and
two Wirth 8.8 m hardrock TBMs from the portals for the other. The TBMs drove
a total of 10.9 km in 19 months and the drill/blast teams completed 25 km, all
in extremely hard granite and gneiss formations of UCS averaging between 150
and 250 Mpa and peaking at 325 Mpa. TBM average progress was 338 m/month with
a best of 518 m. Best day, 35 m in 9.3 hours. The drill/blast teams completed
their own tunnel and broke back onto the TBM tunnel alignment in order to meet
the advancing machines and speed up completion. Sept 1999.
France
Rhone-Alps
- fr/11
High Speed Railway
Public enquiry considered route proposal
which may include 54 km tunnel under Mt Ambin amongst others. March 1998.
Mt Ambin base tunnel now known as AlpeTunnel and 52 km alignment is being defined by long exploration boreholes. Proposed railway will shave 3 h off the journey from Lyon in France to Turin in Italy and is a top priority project within the EU. Route will carry 10.5 million passengers and 14 million t freight each year. Tunnel will take six years to construct and will cost $5 billion. Design is for twin 8 m-diameter tubes with 30 to 50 m separation linked by cross passages. Located mainly in calceschists, metamorphic basement rocks, Triassic dolomites and quartzites with schists, Jurassic marls and limestones, sandstones and flysch. Window access at Venaus (7 km-long), Modane (6.5 km-long), La Praz (8.7 km-long), and St Martin la Porte (1 km-long). $315 million preliminary design investigation programme will include some tunnels between 2001 and 2007, when work should commence on main tunnels for six years. Commissioning scheduled for 2015. Second 12 km-long tunnel required on Italian side to bypass Bussoleno. Sept 1999.
Six deep exploration holes of between 2 and 3 km underway on Alpetunnel alignment between Torino and Chambery by jv AlpExploDrilling comprising Dentag Europe, BRR and Foralith. Currently completing 1.8 km hole at Avrieux using Wirth B5 and will move to Etache for a 3 km hole using a Dentag drillrig. Visit www.foralith.ch for more information. Sept 1999.
Underground station at Modane
will increase projected cost to $6 billion. Preliminary work schedule under
consideration for 2001-2006 financed 50% by EU to include geotechnical investigations
in the Suze valley and construction of adits and pilot tunnels. Decision due
later this year on final alignment. June 2000.
Agreement signed between governments for $10 billion Lyons-Turin (F-I) line with 52 km base tunnel for construction 2006-2015. Access tunnels should start at St Martin la Porte (F), La Praz (F), Modane (F) and Venaus (I) during 2002. Feeder routes will also require tunnels, notably for 14 km beneath Epine (F) and Dullin (F) ranges, 20 km beneath Chartreuse (F) mountains, and 12 km under Belledonne (F) mountains. The 12 km Bussoleno (I) and 8 km Borgone (I) tunnels are also on the main alignment. Visit www.alpetunnel.fr 07/01.
Italian-Swiss committee will promote new $3.5 billion, 160 km-long railway on Paris-Turin alignment with 48.5 km-long tunnel under Grand St Bernard Pass between Martigny and Val d'Aosta. Visit www.cff.ch and www.alpetunnel.fr 22/01.
Invitation to negotiate contract, deadline 3rd September, 2001, for construction of 4 km-long access adit and two investigation tunnels at Modane for Lyon-Turin rail link. Also, prequalification, deadline 6th September, 2001, for engineering design of same. Contact Alpetunnel-GEIE, fax +33 47 960 9704. Visit www.alpetunnel.fr 34/01.
Negotiated procedure, deadline 29th November, 2001, for soil investigation and on site tests as part of the Lyons-Turin HSR. Lot 1 is for excavation of a 2 km-long 72-96 sq m drift to be drilled/blasted. Lot 2 is for two 30-40 sq m tunnels, 1.5 km each. Option for another two tunnels of 500 m and 300 m. Visit http://ted.eur-op.int, document S 206-141380 or contact Alpetunnel GEIE, Chambéry, fax +33 4 79609704. Also visit www.alpetunnel.com 45/01.
Tenders invited by Lyon-Turin Ferroviaire, the former Alpetunnel GEIE, for engineering services to analyse the bids, prepare the contracts, manage and follow up the excavation of a 2,000 m drift (contract 1), and two investigation galleries, 1.5 km to 1.8-2 km (contract 2). Part of the Lyon-Turin basis tunnel. Visit www.alpetunnel.com and www.transalpine.com 49/01.
Tenders for work supervision, deadline 14th January, 2002, for a 4 km drift (contract 1) and two investigation tunnels (contract 2) of 2.5 and 3 km. Visit http://ted.eur-op.eu.int, document S 240-165437 or fax +33 479685659. Visit www.alpetunnel.com and www.transalpine.com 52/01.
Award to a jv of EEG Simecsol, SNCF Ingénierie, Geodata of Italy, and Bonnard et Gardel of Switzerland of an engineering assistance contract for the draft and detailed design and the preparation of documents as part of the La Praz adit and pilot tunnel. The adit is approx. 2.8 km-long for the east option and 3 km for the west one, cross section 70 sq m. The pilot tunnel is approx. 3 km for the east option and 2 km for the west one, cross section 25 sq m. Visit www.alpetunnel.com 04/02.
Two negotiated procedures for the construction and work supervision of the 70 sq m adit and 25 sq m pilot tunnel. Deadlines for construction set to 4th March, 2002 and for work supervision to 21st February, 2002. Visit http://ted.eur-op.eu.int/ojs/en/frame.htm, OJ S 13, document 9950-2002, and OJ S 15, document 11422-2002 or contact Lyon-Turin Ferroviaire, Chambéry, fax +33 4 79685659. Also visit www.alpetunnel.com 05/02.
Negotiated deal for hydrogeological studies for the international section of the Lyon-Turin high speed link between Saint-Jean-de-Maurienne and Cianocco. This section includes the Maurienne-Ambin basis tunnel (52.7 km) and the 12.5 km Bussoleno tunnel. A first report is due in October, 2002. Visit http://ted.eur-op.eu.int/ojs/en/frame.htm, OJ S 43, document 34038-2002, fax +33 4 79685659 or E-mail alpetun@icor.fr with copy to sabine.dallacosta@ltf-sas.com 10/02.
Restricted procedure, deadline 8th April, 2002 for geotechnical studies as part of the draft design for the passenger and freight link across the Belledonne massif. Lot 2 deals with core drills for the Belledonne tunnel. Geology consists of alluvium, glacial deposit, limestone, schists, micaschists, gneiss, granite, etc. Visit http://ted.eur-op.eu.int/ojs/en/frame.htm, OJ S 51, document 39894-2002 or contact Réseau Ferré de France, Lyon, fax +33 472840579. 12/02.
Restricted
procedure, deadline 11th April, 2002 for technical studies dealing with the
draft design of the Belledonne tunnel, civil engineering structures and earthworks.
Visit http://ted.eur-op.eu.int/ojs/en/frame.htm,
OJ S 66, document 51951-2002 or contact Réseau Ferré de France,
Lyon, fax +33 472840579. 15/02.
Eiffage, in jv with Condotte d'Acqua and GRA, has scooped a €82 million
contract to build a 4 km drift in Modane, 3 km of which with a high gradient.
This is the first tunnelling contract. Work has started on 18th March, 2002.
Completion in 2005. Visit www.eiffage.fr
and www.condottespa.it
15/02.
Fiat Engineering has won a contract to draw up preliminary designs for work and safety equipment for the 53 km Turin-Lyon tunnel. The contract is worth €1 million and will be carried out in cooperation with Italferr and French companies Setec, Systra and SNCF Ingénierie. Visit www.fiatengineering.it 20/02.
Award
to a jv of EEG Simecsol, SNCF Ingénierie, Bonnard et Gardel, and Sea
Consulting of a work supervision engineering contract for a 4 km drift (lot
1) and two investigation tunnels (lot 2) of 2.5 and 3 km in Modane and Villarodin-le-Bourget.
Contract value €2.1 million. Visit www.alpetunnel.com
29/02.
Award to a jv of Scetauroute and Antea-Alpina of work supervision engineering
contract for a 2 km drift in Saint-Martin-la-Porte. Contract value €2.37
million. 29/02.
Negotiated procedure, deadline 12th November, 2002 for geophysical exploratory services for the Chartreuse tunnel to identify lignite galleries in Saint-Didier-de-la-Tour and Saint-André-le-Gaz on a length of 2 km and a width of 400 m. Visit http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=en&docid=159061-2002, OJ S 201, or contact Réseau Ferré de France, fax +33 472840579. E-mail alain.colomb@rff.fr 44/02.
Restricted invitation to tender, deadline 14th February, 2003 for core drilling for the 12 km-long Bussoleno tunnel. Lot 1 is for eight vertical boreholes in alluvial ground spread out on a length of 580 m with a maximum depth of 150 m, or ten vertical boreholes on a length of 840 m, maximum depth 200 m. Lot 2 is for six vertical boreholes in rock, length of execution 2,140 m and maximum depth 540 m, or seven vertical boreholes, length 2,720 m and maximum depth 580 m. Lot 3 is for five vertical boreholes in rock on a length of 2,530 m at a maximum depth of 870 m, or four vertical boreholes, maximum depth 950 m, plus one 400 m horizontal borehole, to be executed on a length of 3,100 m. Visit http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=en&docid=202642-2002, OJ S 252, or contact Lyon Turin Ferroviaire, Chambéry, tel. +33 479685666 or 67 and +39 0115579221. E-mail pierre.dhe@ltf-sas.com, franco.gallara@ltf-sas.com and xavier.dermendrail@ltf-sas.com 02/03.
A
JV of Razel, its mother company Bilfinger Berger, Pizzarotti and Granulats Rhône-Alpes
has been commissioned to build the 2,040 m descending drift in Saint-Martin-la-Porte
(lot 1) for €40.4 million. Visit www.ltf-sas-com
and www.razel.fr 11/03.
Open call for bids, deadline 9th April, 2003 for geological investigation and
core drills. Lot 1 is a 1.3 km-deep 30° inclined borehole in the Modane-Chavières
area including data logging, BHTV, and tests. Lot 2 is a 100 m-deep vertical
borehole in the Saint-Julien area including tests. Lot 3 is a 1.1 km-deep vertical
borehole in the Houiller (Orelette) area including data logging, BHTV and tests.
Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=036403-2003,
OJ S 42, or contact Lyon Turin Ferroviaire, Chambéry, fax +33 479609704.
E-mail pierre.dhe@ltf-sas.com for
administrative info and xavier.darmendrail@ltf-sas.com
and nathalie.monin@ltf-sas.com
for technical info. 11/03.
Atlas Copco will rent a Rocket Boomer XL3 C drilling jumbo to the JV composed of Razel, Bilfinger Berger, Pizzarotti and GRA for drill/blast excavation of a 2,040 m drift in Saint-Martin-la-Porte, 7 km from the French entrance of the future base tunnel. This exploratory drift features a variable cross section of 80-100 sq m. The drive will be slightly climbing on the first 900 m and then descending on 1,100 m (8% gradient). Geology consisting of limestone and marls, dolomites, anhydrite, gypsum, sandstone, schists and carbonaceous schists. Up to 169,000 cubic metres of spoil will be removed, 29,000 cu m of concrete and 6,400 cu m of shotcrete will be necessary as well as 2,100 tonnes of steel arches and 77,000 metres of anchoring bolts. Other machinery at the worksite include, in particular, an Atlas Copco Boltec 435H rock bolting rig. Preparatory work started on 4th March, 2003 and the project will last 25 months. The first blast is planned for July 2003. More from franck.boudreault@atlascopco.com. Visit www.atlascopco.fr and www.razel.fr 22/03.
Restricted
call for bids, deadline 4th July, 2003 for geophysical investigation for the
52 km base tunnel and the 12 km Bussoleno tunnel. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=099075-2003,
OJ S 110, or contact Lyon Turin Ferroviaire, Chambéry, fax +33 479609704.
E-mail pierre.dhe@ltf-sas.com and
nathalie.monon@ltf-sas.com 25/03.
Open call for bids, deadline 24th July, 2003 for aeraulics study as part of
the draft design of the 12 km Bussoleno tunnel. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=099055-2003,
OJ S 110, or contact Lyon Turin Ferroviaire, Chambéry, fax +33 479686097
or 5675. E-mail pierre.dhe@ltf-sas.com
and eddy.verbesselt@ltf-sas.com
25/03.
Negotiated procedure, deadline 3rd October, 2003 for engineering studies for the draft design of the passenger and freight line linking the Alpine furrow to Saint-Jean-de-Maurienne. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=139699-2003, OJ S 153, or contact Réseau Ferré de France, Lyon, fax +33 472840579. Also visit www.rff.fr/pages/projets/fiche_projet.asp?code=302 36/03.
Restricted procedure, deadline 29th September, 2003 for construction of the 7 km-long 6 m-diameter Venaus exploratory tunnel, with option for three more kilometres. Overburden of 2 km and 2.5 km for the optional 3 km. To be driven mainly using a hard rock gripper TBM. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=150092-2003 and http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=150093-2003, OJ S 163, or contact Lyon Turin Ferroviaire, Chambéry, fax +33 479685683. E-mail vincenzo.degregorio@ltf-sas.com and lorenzo.brino@ltf-sas.com 37/03.
Two contracts have been awarded for core drills for the 12 km-long Bussoleno tunnel in Italy. RCT won contract 1 for eight vertical boreholes in alluvial ground spread out on a length of 580 m with a maximum depth of 150 m, or ten vertical boreholes on a length of 840 m, maximum depth 200 m. Amount: €323,200. More from rct@mi.nettimo.it. Contract 2 is for six vertical boreholes in rock, length of execution 2,140 m and maximum depth 540 m, or seven vertical boreholes, length 2,720 m and maximum depth 580 m. It is won by Geotecno for €1.9 million. More from mfo@geotecnosrl.it. Contract 3 has been declared void for failing to attract bids within the client's budget. This contract is for five vertical boreholes in rock on a length of 2,530 m at a maximum depth of 870 m, or four vertical boreholes, maximum depth 950 m, plus one 400 m horizontal borehole, to be executed on a length of 3,100 m. Visit www.ltf-sas.com 42/03.
Restricted
call for bids, deadline 21st November, 2003 for core drilling and exploratory
boring for the Bussoleno tunnel (12 km). Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=180607-2003,
OJ S 200, or contact Lyon Turin Ferroviaire, Chambéry, fax +33 479685683.
E-mail pierre.dhe@ltf-sas.com or
xavier.darmendrail@ltf-sas.com
44/03.
A JV between Scetauroute and Metropolitana Milanese has secured a €108,700
contract to conduct an aeraulics study as part of the draft design of the 12
km Bussoleno tunnel. Visit www.scetauroute.fr
and www.metropolitanamilanese.it
44/03.
Restricted invitation to tender, deadline 8th December, 2003 for environmental measurements for the Venaus exploratory tunnel. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=185215-2003, OJ S 205, or contact Lyon Turin Ferroviaire, Chambéry, fax +33 479685683 and +39 0122641052. E-mail pierre.dhe@ltf-sas.com and piergiuseppe.gilli@ltf-sas.com 45/03.
Open invitation to tender, deadline 5th January, 2004 for a 500 m vertical or inclined core drill. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=192010-2003, OJ S 213, or contact Lyon Turin Ferroviaire, Chambéry, fax +33 479685683. E-mail sgt.dde-isere@equipement.gouv.fr 46/03.
Geophysik
GGD won a €191,720 contract for preparing seismic profiles from core drills
F65 and F75 for the base tunnel, a €184,460 contract for preparing seismic
profiles from core drills S42, S49 and S8 for the Bussoleno tunnel, and a €55,260
contract for evaluation of the depth of the vertical faults for the base tunnel.
Visit www.geophysik-ggd.com
51/03.
Geoexpert won a €42,700 contract for two hybrid seismic profiles, 1 km
and 600 m in length, for the base tunnel. Visit www.geoexpert.ch
51/03.
Geoinvest won a €33,600 contract for electrical profiles for the Bussoleno
tunnel. Visit www.geoinvest.it
and www.ltf-sas.com 51/03.
Open invitation to tender, deadline 14th April, 2004 for project construction management for the Venaus exploratory tunnel. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=026791-2004, OJ S 30, or contact Lyon Turin Ferroviaire, Chambery, fax +33 479685683. E-mail vincenzo.degregorio@ltf-sas.com 10/04.
Negotiated
procedure, deadline 2nd July, 2004 for assistance to the client for the reference
draft design, the detail design of the Italian part and the public inquiry in
France and Italy. Contract 5 deals with tunnels. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=087067-2004,
OJ S 106, or contact Lyon Turin Ferroviaire, Chambery, fax +33 479685683. E-mail
vincenzo.degregorio@ltf-sas.com
or lorenzo.brino@ltf-sas.com
25/04.
Negotiated procedure, deadline 19th July, 2004 for assistance to the client
for the reference draft design for the international section of the base tunnel
between Saint-Jean-de-Maurienne, France and Bruzolo, Italy. The reference draft
design is an intermediate stage between the conceptual design and the detail
design. There are seven contracts. Contract 0 is for general coordination. Contract
A1 deals with operation and maintenance, contract A2 with safety, contract B1
with civil engineering, contract B2 with geology, contract B3 with railway and
non-railway equipment and contract B4 with environment. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=094328-2004,
OJ S 112, or contact Lyon Turin Ferroviaire, Chambery, fax +33 479685683. E-mail
vincenzo.degregorio@ltf-sas.com
or geraldine.berthier@ltf-sas.com
25/04.
Negotiated procedure, deadline 28th June, 2004 for making compatible urbanism
documents (land use plan, development plan, maps, etc.) between Saint-Jean-de-Maurienne
and the Italian border as part of the public inquiry. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=094345-2004,
OJ S 112, or contact Lyon Turin Ferroviaire, Chambery, fax +33 479685683. E-mail
vincenzo.degregorio@ltf-sas.com,
jacques-ricard@ltf-sas.com,
geraldine.berthier@ltf-sas.com
or nicole.delbe@ltf-sas.com 25/04.
Information meetings will be held in Paris on 17th June and in Rome on 18th
June. Visit www.ltf-sas.com/fr/couponreponseapr.pdf
for registration to these meetings. 25/04.
Qualification procedure for safety studies as part of the reference draft design for the international section of the base tunnel between Saint-Jean-de-Maurienne, France and Bruzolo, Italy. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=095916-2004, OJ S 114, or contact LTF, Chambery, fax +33 479685683. E-mail vincenzo.degregorio@ltf-sas.com, stephane.bouquier@ltf-sas.com, geraldine.berthier@ltf-sas.com or nicole.delbe@ltf-sas.com 26/04.
Negotiated procedure, deadline 16th August, 2004 for a 800 m inclined core drill for the base tunnel. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=105133-2004, OJ S 124, or contact Lyon Turin Ferroviaire, Chambery, fax +33 479685683. 28/04.
Negotiated procedure, deadline 15th September, 2004 for compliance control of the reference draft design of the French-Italian section between Saint-Jean-de-Maurienne and Bruzolo. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=107876-2004, OJ S 127, or contact Lyon Turin Ferroviaire, Chambery, fax +33 479685683. E-mail vincenzo.degregorio@ltf-sas.com, lorenzo.brino@ltf-sas.com, geraldine.berthier@ltf-sas.com or nicole.delbe@ltf-sas.com 29/04.
Negotiated procedure, deadline 1st
September, 2004 for construction by means of a TBM of the 7 km Venaus exploratory
tunnel with a cover of 2 km, with option for three more kilometres with a cover
of 2.5 km. This is a re-tender as the previous tender process has been declared
void. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=129218-2004,
OJ S 149, or contact Lyon Turin Ferroviaire, Chambery, fax +33 479685683. 35/04.
Negotiated procedure, deadline 1st September, 2004 for construction of the 3
km Modane access adit, with a 12% gradient. This is a re-tender further to the
cancellation of a previously awarded contract, when one kilometre had been bored.
Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=129216-2004,
OJ S 149, or contact Lyon Turin Ferroviaire, Chambery, fax +33 479685683. Subscribe
to E-News
Weekly 28/2004 & 24/2004. 35/04.
Negotiated procedure, deadline 17th December, 2004 for construction of the La Praz adit, 2.5 km in length with a 12% gradient, for ground exploration and access to the future base tunnel. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=191764-2004, OJ S 222, or contact Lyon Turin Ferroviaire, Chambery, fax +33 479685683. 48/04.
A consortium formed by Arcadis, Metropolitane Milanese, Scetauroute and Semaly has won a EUR2 million contract to perform extensive safety surveys on two tunnels, including the 53 km base tunnel, on the future Lyon-Turin line between France and Italy. The consortium will study the possible effects of an accident inside the tunnel with dangerous goods including toxic gases or flammable liquids and help determine whether the planned safety measures inside and around the tunnels are sufficient to mitigate the effects of such events. The survey will be finalised in May 2005. The railway line will be used for passenger transport, including high speed rail travel, and for freight transportation. The latter will also include the transportation of dangerous goods and trucks. Visit www.ltf-sas.com, www.arcadis-global.com, www.metropolitanamilanese.it, www.scetauroute.com and www.semaly.com 51-52/04.
Razel, its parent company Bilfinger Berger, and Pizzarotti secured a EUR51.4 million contract to finish the Modane exploratory tunnel to access to the future base tunnel. This award is subsequent to a rebid further to the cancellation of a previously awarded contract, after 1 out of 4 km had already been blasted. Subscribe to E-News Weekly 28/2004. Visit www.razel.fr, www.bilfinger.de and www.pizzarotti.it 02/05.
Periodic notice for
construction of the Modane exploratory tunnel and access adit to the future
base tunnel. This is the third time the project is tendered. 2,914 m of tunnel
remains to be drilled. Last year, LTF decided to terminate the initial contract
awarded to Eiffage and Condotte d'Acqua. Then, the project was retendered and
awarded to Razel, Bilfinger Berger and Pizzarotti at the end of 2004. However,
the initial contractors appealed against the award at the Grenoble administrative
court which, in an injunction order taken on 22nd December, 2004 obliges LTF
to relaunch the bid procedure, for the third time. Estimated cost: EUR55 million.
Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=019845-2005,
OJ S 20, or contact Lyon Turin Ferroviaire, Chambery, fax +33 479685683. E-mail
sylvie.dufour@ltf-sas.com, jean-yves.peltier@ltf-sas.com
and christian.fournier@ltf-sas.com.
Subscribe to E-News Weekly 28/2004.
05/05.
Periodic notice for construction of the 2.5 km La Praz exploratory tunnel and
access adit to the future base tunnel. This is the second time the project is
tendered as the first bidding procedure has been declared void by LTF. Estimated
cost: EUR51 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=019850-2005,
OJ S 20, or contact Lyon Turin Ferroviaire, Chambery, fax +33 479685683. E-mail
sylvie.dufour@ltf-sas.com, jean-yves.peltier@ltf-sas.com
and christian.fournier@ltf-sas.com.
05/05.
Periodic notice for lead engineering for construction of the 2.5 km La Praz
exploratory tunnel and access adit to the future base tunnel. Estimated cost:
EUR3 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=019850-2005,
OJ S 20, or contact Lyon Turin Ferroviaire, Chambery, fax +33 479685683. E-mail
sylvie.dufour@ltf-sas.com, jean-yves.peltier@ltf-sas.com
and christian.fournier@ltf-sas.com.
05/05.
Periodic notice for safety coordination during construction of the 2.5 km La
Praz exploratory tunnel and access adit to the future base tunnel. Estimated
cost: EUR150,000. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=019847-2005,
OJ S 20, or contact Lyon Turin Ferroviaire, Chambery, fax +33 479685683. E-mail
sylvie.dufour@ltf-sas.com, jean-yves.peltier@ltf-sas.com
and christian.fournier@ltf-sas.com.
05/05.
The construction of the 6 m-diameter Venaus investigatory tunnel under the Ambin massif near Susa has been commissioned to a JV headed by CMC and including Strabag, Bentini Costruzioni, Cogeis and Geotecna for EUR84.3 million. The contract awarded by Lyon Turin Ferroviaire (LTF) is for a 7 km tunnel, with option for a further 3 km. Cover above the tunnel of approximately 2,000 m (2,500 m for the optional three kilometres). A hard rock Gripper TBM will be used. Work to commence next spring to last three years. Visit www.ltf-sas.com, www.cmcra.it, www.strabag.at and www.cogeis.it 07/05.
Negotiated procedure, deadline 4th April, 2005 for construction of the Modane exploratory adit (2.9 km) to the future base tunnel. Tender estimate: EUR55 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=040807-2005, OJ S 42, or contact LTF, Chambery, fax +33 479685683. E-mail jean-yves.peltier@ltf-sas.com or christian.fournier@ltf-sas.com 10/05.
Negotiated procedure, deadline 26th April, 2005 for engineering, including work management during construction of the 2.5 km La Praz exploratory tunnel. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=060119-2005, OJ S 62, or contact Lyon Turin Ferroviaire, Chambery, fax +33 479685683. E-mail jean-yves.peltier@ltf-sas.com and sylvie.dufour@ltf-sas.com 14/05.
Periodic notice for
excavation of the 2.5 km La Praz access and exploratory adit in Savoy. Gradient
12%. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=076907-2005,
OJ S 79, or contact Lyon Turin Ferroviaire, Chambery, fax +33 479685683. E-mail
descenderie-la-praz@ltf-sas.com
18/05.
Negotiated procedure, deadline 26th May, 2005 for safety and health coordination
during construction of the 2.5 km La Praz access and exploratory adit. Visit
http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=075853-2005,
OJ S 78, or contact Lyon Turin Ferroviaire, Chambery, fax +33 479685683. E-mail
jean-yves.peltier@ltf-sas.com,
sylvie.dufour@ltf-sas.com and
geraldine.berthier@ltf-sas.com
18/05.
Periodic notice for construction supervision of the 2.9 km Modane access and exploratory adit in Savoy. Tender estimate: EUR3 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=083536-2005, OJ S 86, or contact Lyon Turin Ferroviaire, Chambery, fax +33 479685683. E-mail moe-modane@ltf-sas.com 19/05.
Negotiated procedure, deadline 13th June, 2005 for construction of the La Praz access and exploratory adit, approximate length 2.5 km. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=089076-2005, OJ S 90, or contact LTF, Chambery, fax +33 479685683. E-mail descenderie-la-praz@ltf-sas.com 21/05.
Lyon
Turin Ferroviaire has awarded for EUR52.7 million, after a third bidding process,
the completion of the Modane-Villarodin Bourget access adit to the Lyon-Turin
base tunnel to Razel (leader), its mother company Bilfinger Berger, and Pizzarotti.
The Modane access adit is located nearly half-way on the future base tunnel
alignment (at 28.5 km from the west portal). It spans 4 km, whereof 1,086 m
has already been excavated between mid-2002 and May 2004, as part of a first
contract later cancelled. Maximum gradient: 12%. Section of 65 to 80 sq m. Estimated
time for completion is three years. Read E-News
Weekly 28/2004. Visit www.lyonturin-ferroviaire.com/,
www.razel.fr and www.pizzarotti.it
38/05.
The La Praz access adit will be built by Spie Batignolles TPCI (leader), its
affiliate Sotrabas, Ghella and Cogeis, for EUR61.5 million. This adit is located
20 km from the west entrance of the future base tunnel. It is 2,572 m long.
Section: 80 sq m. Construction is estimated to take three years. Visit www.lyonturin-ferroviaire.com,
www.spiebatignolles.fr,
www.ghella.com and www.cogeis.it
38/05.
Negotiated procedure, deadline 17th November, 2005 for construction management of the Modane exploratory tunnel. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=194558-2005, OJ S 197, or contact Lyon Turin Ferroviaire, Chambery, fax +33 479685683. E-mail moe-modane@ltf-sas.com 42/05.
Geos and D'Appolonia secured a EUR509,000 contract for safety studies as part of the reference draft design for the international section of the base tunnel between Saint-Jean-de-Maurienne, France and Bruzolo, Italy. Visit www.geos.tm.fr and www.dappolonia.it 43/05.
The Razel / Bilfinger Berger / Pizzarotti JV awarded Atlas Copco a contract to supply four drill rigs for the Modane-Villarodin Bourget access adit. The fleet includes one Rocket Boomer WL3 C, to be delivered this week, for drilling blast holes and for ground investigation; one Rocket Boomer L2 C, delivered in early November, a versatile machine capable of drilling holes for traditional 9 m roof bolting and blast holes; one Boltec LC, to be delivered in January 2006, for mechanised bolting; and one Diamec U6, to be delivered by the end of November, for core drilling ahead of the face. The machines will be used to complete the job. 1,086 m of 4 km has been excavated on a previous contract before its cancellation due to a disagreement between the contractors and the client. Click fr/11. Visit www.atlascopco.com and www.lyonturin-ferroviaire.com 47/05.
Atlas Copco secured a contract to supply four drilling rigs for the 2,572 m-long 80 sq m La Praz access tunnel to the future Maurienne-Ambin base tunnel on the Lyon-Turin high speed link. The machines include one Rocket Boomer WL3 C for tunnelling; one Rocket Boomer L2 C, a versatile machine for traditional bolting and bolting of 9 m bolts according to specifications, tunnelling and ground investigation drillling; and two Boltec LCs for mechanised bolting. The deliveries are scheduled between January and March 2006. The L2 C has been delivered at the site on 14th January. Drilling started on 16th January. With the La Praz deal, Atlas Copco pockets the third of all three tunnelling equipment contracts for the three access adits (in Saint-Martin-la-Porte, Modane/Villarodin-Bourget and La Praz) on the French side of the project. Read our Lyon-Turin focus in the special 200th issue of E-News Weekly, tunnelbuilder's e-mail newsletter by subscription. Click fr/11. Visit www.atlascopco.com, www.boomer-rig.com, www.rockreinforcement.com and www.lyonturin-ferroviaire.com 04/06.
Negotiated
procedure, deadline 27th March, 2006 for three ground investigation drillings
(F130, F131, F132) for the base tunnel in the Maurienne valley. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=053741-2006,
OJ S 51, or contact LTF, Chambery, fax +33 479685683. E-mail jean-yves.peltier@ltf-sas.com
12/06.
Negotiated procedure, deadline 27th March, 2006 for three ground investigation
drillings (F133, F134, F135) for the base tunnel in the Maurienne valley. Visit
http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=053743-2006,
OJ S 51, or contact LTF, Chambery, fax +33 479685683. E-mail jean-yves.peltier@ltf-sas.com
12/06.
Negotiated procedure, deadline 27th March, 2006 for a ground investigation drilling
(F136) for the base tunnel in the Maurienne valley. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=053748-2006,
OJ S 51, or contact LTF, Chambery, fax +33 479685683. E-mail jean-yves.peltier@ltf-sas.com
12/06.
Negotiated procedure, deadline 27th March, 2006 for a ground investigation drilling
(F140) for the base tunnel in the Maurienne valley. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=053750-2006,
OJ S 51, or contact LTF, Chambery, fax +33 479685683. E-mail jean-yves.peltier@ltf-sas.com
12/06.
Negotiated procedure, deadline 3rd May, 2006 for environmental studies for the
Lyon Saint-Exupery-Chapareillan section, divided into two subsections: Lyon
Saint-Exupery to entrance of the Chartreuse tunnel (54 km whereof 16 km of tunnel)
and entrance of the Charteuse tunnel to Chapareillan (23 km of tunnel). Visit
http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=083764-2006,
OJ S 79, or contact RFF, Lyon, fax +33 472846571. E-mail sylvie.girard@rff.fr
18/06.
Negotiated procedure, deadline 3rd May, 2006 for environmental studies for the
Laissaud - Saint-Jean-de-Maurienne section, divided into two subsections: the
Belledonne tunnel (20 km) and two route alternatives in La Chambre in Saint-Jean-de-Maurienne
(8 km at grade and a 4 km tunnel under the Rocheray massif or 3 km at grade
and a 9 km tunnel under Rocheray). Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=083762-2006,
OJ S 79, or contact RFF, Lyon, fax +33 472846571. E-mail sylvie.girard@rff.fr
18/06.
Negotiated procedure, deadline 3rd May, 2006 for geological investigations for
the Lyon-Chapareillan section and the Laissaud - Saint-Jean-de-Maurienne section.
Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=083760-2006,
OJ S 79, or contact RFF, Lyon, fax +33 472846571. E-mail sylvie.girard@rff.fr
18/06.
A EUR2.8 million contract for construction management of the remaining 2.9 km of the Modane-Villarodin Bourget access adit to the Lyon-Turin base tunnel went to Lombardi. Read E-News Weekly 2/2006. Visit www.lombardi.ch and www.ltf-sas.com 21/06.
Negotiated procedure, deadline 14th June, 2006 for geological surveying, measurements and mapping in several areas of the international section of the Lyon-Turin base tunnel. Read E-News Weekly 2/2006. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=110595-2006, OJ S 103, or contact LTF, Chambery, fax +33 479685683. E-mail geraldine.decarre@ltf-sas.com 24/06.
CSI
has bagged a EUR583,000 contract for three ground investigation drillings (F130,
F131, F132) for the Lyon-Turin base tunnel in the Maurienne valley. 30/06.
Foraco received a EUR3.6 million contract for three ground investigation drillings
(F133, F134, F135) for the Lyon-Turin base tunnel in the Maurienne valley. Visit
www.foraco.com 30/06.
COFOR received a EUR1.7 million contract for one ground investigation drilling
(F136) for the Lyon-Turin base tunnel in the Maurienne valley. They also received
another contract, also worth around EUR1.7 million, for another ground investigation
drilling (F140) for the Lyon-Turin base tunnel in the Maurienne valley. Visit
www.spac.fr 30/06.
Restricted call for tenders, deadline 30th October, 2006 for follow-up of ground
and infrastructure movements, and geodesy for the La Praz, Modane and Saint-Martin-la-Porte
access adits to the Lyon-Turin base tunnel. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=195876-2006,
OJ S 184, or contact LTF, Chambery, fax +33 479685683. E-mail delphine.croizier@ltf-sas.com
42/06.
Antea, BRGM and Geodata
secured a EUR337,600 contract for geological surveying, measurements and mapping
in several areas of the international section of the Lyon-Turin base tunnel.
Visit www.antea-ingenierie.fr,
www.brgm.fr and www.geodata.it
11/07.
Atlas Espace Dimension (AED), Gascogne Génie Civil and Geoworks bagged
a EUR693,200 contract to follow up ground and infrastructure movements and perform
geodesy works at the La Praz, Modane and Saint-Martin-la-Porte access adits
to the Lyon-Turin base tunnel. Visit www.aed-montagne.com,
www.ggctopo.com and www.geoworks.com
11/07.
Negotiated procedure, deadline 7th May, 2007 for studies (seven contract packages) for the international section of the Lyon-Turin high speed line. These seven contracts are for operation and maintenance (lot 1), safety (lot 2), civil engineering, geology and environment (lot 3), railway and other equipment (lot 4), follow-up for the fulfilment of these contracts (lot 5), specialist assistance (lot 6), and economic and socio-economic studies (lot 7). Read E-News Weekly 15/2007, 7/2007, 1/2007, 2/2006, 50/2005, 46/2005 & 34/2005. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=86272-2007, OJ S 70, or contact LTF, Chambery, fax +33 479685683. E-mail michel.bogacz@ltf-sas.com 16/07.
Negotiated call for tenders, deadline 10th September, 2007 for engineering services for the approx. 80 km international cross-border section between Saint-Jean-de-Maurienne in France and Susa valley in Italy. The 53 km base tunnel is the major challenge on that section. The studies deal with operation and maintenance (lot 1), safety (lot 2), civil engineering, geology and environment (lot 3), railway technology and other equipment (lot 4), construction follow-up (lot 5), specialised consultancy (lot 6), economic and socio-economic studies (lot 7), geodesy and topography (lot 8), soil and rock exploration and surface exploration (lot 10). Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=194966-2007, OJ S 156, or contact LTF, Chambery, fax +33 479685683. E-mail michel.bogacz@ltf-sas.com 34/07.
Bombay - in/16
Sewage Outfall
TBM
Dyckerhoff & Widmann halfway through contract to provide two 3 km-long, 3 m-diameter sewer outfalls using single Wirth TBM in basalt. October 1999.
India
Bombay - in/17
Water Supply
TBM
Bidding for final lot of four contracts that have been undertaken since mid-80s to provide fresh water to Bombay treatment plants. This package is for 12 km of 3.5 m-diameter tunnel in basalt. First lot completed by Gammon using a Demag TBM; second and third packages completed by Hindustan Construction Company using a Wirth TBM. October 1999.
$35
million contract awarded to Hindustan Construction Company for 12 km-long tunnel
to be constructed at 60 m depth to supply 355 million litre/day of water to
Mumbai and district. Tata Consulting Engineers evaluated bids for Brihanmumbai
Municipal Corporation. Sept 2000.
Tunnelling commenced October, 1996 and is due for completion end-2002. Seven
running tunnels are involved as follows, from Bologna to Firenze: Pianoro (10.7
km), Sadurano (3.77 km), Monte Bibele (9.1 km), Raticosa (10.39 km), Scheggianico
(3.54 km), Firenzuola (15.06 km), and Vaglia (18.35 km). Also 12 access tunnels
total length 8.8 km are required to split the route into sections of not more
than 3.5 km.
Main contractor Cavet reports 20 km of 71 km alignment has been excavated to date, 60 % of which has also been fully lined. Some 32 x 130 m2 faces open at present. The access tunnels are generally 60 m2 with 14 % maximum gradient, and 2.4 km have been fully lined on Raticosa tunnel due to poor ground conditions. North portal of Firenzuola at San Pellegrino is being driven at 21 m wide for 600 m to accommodate siding for spare train. All equipment used in these tunnels is flameproofed. October 1999.
Boring of 6.5 km Vaglia segmentally-lined service tunnel to commence in June using Wirth double telescopic shield TBM from a quarry near the Firenze end of the proposed 18 km-long main tunnel. Geology is marly limestones and lime marls with marly strata. Contract also includes 2.7 km of access adits. The northernmost 7.5 km of Vaglia running tunnel was completed a year ago, and completion is now scheduled for 2005. Visit www.wirth-drilling.com May 2000.
Restricted tendering for construction of section of 9.243 km Monte Bibele tunnel, deadline 1st August, 2000. Contact Cavet, fax +39 051 651 8327 and visit www.rocksoil.com July 2000.
Tunnel advance on 32 faces currently averaging 1.6 km/month with less than 5 % variation from budgeted cost. Crown excavation and lining of 728 m-long San Pellegrino chamber at the north end of Firenzuola tunnel nearly completed at 2-3 m/day average advance. Final design of 18 km-long Vaglia tunnel at south end of alignment includes 9.26 km-long x 5.6 m i.d. service tunnel to be driven using double telescopic shield Wirth TBM type 630 E/TS erecting 250 mm-thick trapezoidal reinforced concrete segmental lining. This will run parallel to main tunnel for 6.5 km, with connections at 250 m intervals. Main tunnel currently underway from Carlone access and north portal at 7 m/day of finished tunnel in marly limestones and lime marls with marly strata. Visit www.rocksoil.com and www.wirth-drilling.com July 2000.
Rocksoil
has reported progress on the Bologna-Firenze (BO-FI) section of the Italian
high speed railway. Around 59 km of main and service tunnels, constituting 64%
of the total, and 10 km of access adits, have been completed.
Some 7.2 km of the 10.71 km-long Pianoro tunnel is complete, and work continues
on four faces. The 418 m-long caverns required for interconnection with the
existing railway are still in design.
The 3.77 km-long Sadurano has been completed at an average of 4 m/day of finished
tunnel.
Some 5.87 km of the 9.1 km Monte Bibele has been excavated, with 3 m/day average
advance from the north portal, and 1.66 m/day from the south. Work has started
from the base of the 1.54 km-long Quinzano adit on two faces, advancing around
1.2 m/day apiece.
At Raticosa, 7.2 km of the 10.37 km-long main tunnel has been driven, and work
is proceeding on the north face and two faces each from the Osteria and Castelvecchio
adits.
Excavation of the 3.56 km-long Scheggianico was completed in 1999, and lining
is in progress, and 75% complete.
The 14.34 km-long Firenzuola is being developed in sections, with the San Pellegrino
chamber and 3 km of main tunnel at the BO end complete, together with 1.8 km
in each direction from the San Giorgio adit, and 300 m in each direction from
the Marzano adit. The central 1.5 km Osteto adit is also complete, and faces
are being formed at its base. Four faces are being worked at present, one from
Rovigo, two from Marzano, and one from San Giorgio.
The 528 m-long Borgo Rinzelli shallow tunnel near Mugello was completed in May,
2001, and the adjacent and similar 654 m Morticine is underway.
Excavation of the 18 km-long Vaglia main running tunnel is 50% complete, and
the BO end is advancing off a single face from the Carlone adit at 5.8 m/day.
The FI section is still in design. Some 1.6 km of the 9.26 km-long, 5.6 m-internal
diameter Ginori service tunnel has been completed using an innovative Wirth
TBM which is setting 25 cm-thick trapezoidal lining segments. The service tunnel
will run parallel with the main tunnel with connections at 250 m intervals.
More from rocksoil@tin.it. Visit www.rocksoil.com
and www.tav.it 44/01.
Italferr appointed Astaldi to build the underground station for high speed trains in Bologna. The 640 m-long 40 m-wide station will be dug 23 m under the surface on three levels. Contract value: €300.6 million. Visit www.italferr.it, www.tav.it and www.astaldi.it 43/03.
Open
call for tenders, deadline 24th March, 2006 for executive design, work supervision
and construction of the high speed line in Florence for the Bologna-Florence
fast trains. The new 9 km-long line includes a 2 x 5,574 m-long single-track
tunnel to be built by TBM, the new underground station in Belfiore (600 m),
trenches and cut-and-cover tunnels at the north portal in Rifredi (1,768 m)
and the start shaft in Campo di Marte. Total value: EUR915.3 million. Visit
http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=06936-2006,
OJ S 6, or contact Italferr, fax +39 0649752445. E-mail appalti.italferr@legalmail.it.
Visit www.italferr.it/gare/1018-ALL5b-ELENCO-VOCI.pdf
and
www.italferr.it/gare/1018-ALL1-SCHEMA-CONVENZIONE.pdf
04/06.
The successful bidder
for the executive design and construction of the high speed rail tunnel under
Florence is a JV headed by Coopsette, with consortium Ergon Engineering and
Contracting, whose partners are CO.ES.TRA., Inso and the Etruria consortium.
The contract is worth EUR685 million and includes a 2 x 5,574 m-long single-track
TBM-built tunnel from Ponte al Pino to Castello, the new underground station
in Belfiore (600 m), trenches and cut-and-cover tunnels at the north portal
in Rifredi (1,768 m) and the start shaft in Campo di Marte. The TBMs are scheduled
to commence boring in the second half of 2008. Visit www.coopsette.it,
www.coestra.it, www.inso.it,
www.gruppoconsorzioetruria.com
13/07.
Italy
Trento - it/27
Highway
Initial design for 3.5 km single tube tunnel between Mezzolombardo and La Rupe in the autonomous province of Trento-Higher Adige. Exploratory/service tunnel to be driven at 4.8 m-diameter on parallel alignment in about one year's time, probably using roadheader in dolomite. Expect invitation to tender for main tunnel in 2002. October 1999.
Restricted invitation to tender for excavation of 4.8 m-diameter investigation tunnel in dolomite for 3.5 km-long Mezzolombardo road tunnel. Contact PAT in Trento, fax +39 046 123 7737. Notice appeared 8th February, 2001 in European Gazette and at http://ted.eur-op.eu.int 08/01.
Excavation of 3.7 km-long pilot tunnel started early March by a jv of Giolai Costruzioni and De.Mo.Ter, east of Mezzolombardo between north Trento and Rocchetta. Outer diameter of 5.2 m and inner diameter of 4.9 m. South portal is located nearby Rupe and north portal next to the crossroads between provincial road 64 'Fai della Paganella' and SS 43 in Val di Non. The contractors are using a Wirth TBM. Design by Studio Geoingegneria. Completion expected in September 2002. Tenders for the main tunnel to be invited in 2003. Visit www.wirth-europe.com 36/02.
Open call for tenders, deadline 17th February, 2004 for design and build contract for the Trento north-Rocchetta road link, section Zambana Vecchia-connection with trunk road SS 43 to Fai della Paganella. Includes the Rupe tunnel, a 3,710 m-long single-tube tunnel, whereof 500 m will be bored in Ladin dolomites, 400 m in clay, 350 m in Raibl dolomites and 2,460 in main dolomites. Cross section: 155 m², width: 14.2 m and height: 8.4 m. A 5 m-diameter pilot tunnel has been excavated parallel to the future tunnel and will be used as an emergency tunnel when the new tunnel opens. Excavation cost: €33 million. Financing by Trento province. Time frame: 1,200 days from awarding date. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=186505-2003, OJ S 207, or contact Provincia Autonoma di Trento, Trento, fax +39 0461496460. E-mail rita.pancher@provincia.tn.it 47/03.
Restricted
call for tenders, deadline 28th September, 2005 for safety coordination during
construction, measurements and operating management for the Trento north-Rocchetta
roadway, section Zambana Vecchia-connection with road SS 43 to Fai della Paganella.
The project includes the 3,710 m-long Mezzolombardo single-tube tunnel, whereof
500 m will be bored in Ladin dolomites, 400 m in clay, 350 m in Raibl dolomites
and 2,460 in main dolomites. Cross section: 155 sq m. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=145944-2005,
OJ S 146, or contact Provincia Autonoma di Trento, Trento, fax +39 0461496460.
35/05.
Green
light given by the technical committee for public works to construction of
section Zambana Vecchia-Connection with road SS 43 to Fai della Paganella
on the North Trento-Rocchetta section in Trento province. The project has
been modified to include a twin bored tunnel in Mezzolombardo under Mount
Corno, while only a single bored tunnel was planned initially. Work to start
on 12th April for a duration of 1,250 days. The tunnel is also named Rupe.
The north tunnel to Valle di Non is 3,633 m long (1,338 metres straight, 1,386
metres in curves and 908 metres of gradual change from straight to curved
alignment). The south tunnel to Trento is 3,655 m long (1,436 metres straight,
1,409 of curves and 808 metres of gradual change from one type to the other).
Maximum gradient of 1.63% in both tunnels. In view of the second bore added
to the bypass, construction will cost EUR84,357,000. Tunnelling cost, including
the cross passages between the two bores, iwill amount to EUR5,700 per metre.
Click it/27.
15/06.
A
JV formed by Scetauroute, Presents, ATA Engineering, Studio Geo-Ingegneria
and Stain Engineering received a EUR2.6 million contract for safety coordination
during construction, measurements and operating management for the Trento
north-Rocchetta roadway, section Zambana Vecchia-connection with road SS 43
to Fai della Paganella. The project includes a twin-tube tunnel under Monte
Corno in Mezzolombardo, lengths of 3,633 m and 3,655 m. Click it/27.
Visit www.scetauroute.fr,
www.presents.fr, www.atagroup.com
and www.stain-web.com/index2.html
26/06.
The tunnel is built by Collini and Cossi Costruzioni, using a Hitachi Zaxis
350 excavator equipped with hydraulic hammer (north tunnel) and an Atlas Copco
H 175 jumbo in a first stage at the south tunnel (500 metres) before shifting
to a modern WL3C drill rig. Visit www.atlascopco.com
and www.hitachi-c-m.com/global/products/index.html
26/06.
Italy
Castellanza - it/33
Railway
Restricted invitation to tender for construction of 4 km-long railway line
with 2 km tunnel. Deadline 28th February, 2000. Contact Ferrovie Nord, Milan,
fax +39 02 869 2838. January 2000.
Restricted tendering, deadline 1st March, 2002 for the construction of two shield-driven tunnels, 3.7 km-long, under river Olona, four connecting tunnels to be bored using traditional methods, and eight shafts (launch and exit shafts, ventilation, emergency exit, etc.). Budget of €46.6 million. Visit http://ted.eur-op.eu.int/ojs/en/frame.htm, OJ S 16, document 11783-2002 or contact Ferrovie Nord Milano, Milan, fax +39 028691231. 05/02.
Strabag, Torno Internazionale, Cogeis and Romagnoli secured a EUR36.7 million contract from Ferrovie Nord Milano (FNM) to sink underground the tracks in Castellanza, including 2 x 1,855 m of bored tunnel and 2 x 1.9 km in cut-and-cover. The bored tunnel will be dug using a revamped 8.15 m-diameter Wirth TBM, previously used on the Jubilee Line extension in London. Finished diameter will be 7.15 m. Lining with 30 cm-thick concrete segments, eight pieces plus the key per ring. The launch shaft is under construction. TBM start in June 2005 for completion in June 2006. Also four cross passages between both tubes. Visit www.wirth-europe.de, www.strabag.at, www.torno.com, www.cogeis.it and www.romagnoli.net 09/05.
Spain
Madrid-Barcelona - es/20
High Speed Railway
Breakthrough of 5.292 km tunnel between Huermeda and Paracuellos
and work under way on another 1.82 km drive from Santa Maria de Huerta monastery
to Arcos de Jalon. Further extension to connect Alicante and Albacete mooted.
Nov 1998.
44 contracts involve 22 tunnels of total length 22 km. Wirth 12.47 m-diameter reaming TBM has completed 2.5 km of 4.78 km Paracuellos tunnel working south to north. Contractors are FCC and Necso for client GIF. More information from jmfdcas@iies.es February 2000.
Wirth reaming TBM
nearing breakthrough at Paracuellos after 2.8 km drive in which 7 m/day target
was often exceeded with maximum advance 22.4 m/day recorded. Roof and sides
shotcreted on advance using CIFA track-mounted snorkel mounted close to reamer
head. Circular steel arches set 6 m behind face. Aliva wheeled shotcrete jumbo
in invert. Large material +20 cm is screened at TBM and trucked away while
smaller material is conveyed. Any rock needed for backfilling invert is ploughed
of the belt and the remainder is used for embankments or dumped. Concreting
underway with gantry erecting welded PVC membrane ahead of concrete forms
achieving 170 m/week. For the record, the pilot drive by Murer used their
Wirth 4.7 m TBM at 40 m/day in the pre-Cambrian rocks with black schist and
graphite covered by quartzite and some sandstone. Visit www.gif.es
June 2000.
Eighth section of Madrid-Zaragoza stretch under construction by Necso with
1.82 km-long x 137 sq m Sagides tunnel in mixed ground conditions due for
completion March, 2001 using drill/blast and roadheader. Visit www.necso.es
December 2000.
Open invitation to tender, deadline 19th February, 2001, for two twin tunnels, 1.72 km and 415 m long, in Tarragona on Lerida-Barcelona line. Visit www.gif.es 06/01.
Tenders imminent for construction of $800 million connection to Barcelona on alignment Cornella-Airport-Sants-La Sagrera, requiring three major 11.2 m-diameter EPB bored single tunnels in sands, clay and mud of lengths 4.5 km, 7.3 km and 4 km, with 18 km of cut and cover and three single-track junctions. Awards expected end-2001 for start Spring, 2002 and completion end-2004. Visit www.gif.es 26/01.
Necso appointed to construct subsection VII-B of the Lleida-Barcelona high-speed link between Roda de Barà and El Vendrell for Pta5.95 billion (Euro35.78 million). Two twin tunnels of 1,750 m required. Time frame of 26 months to build full stretch. Visit www.necso.es 41/01.
Call for bids imminent further to government approval of the 2.9 km Sant Llorenç d'Hortons-Sant Esteve Sesrovires section in Barcelona province. The section requires to build four tunnels totalling 2,083 metres. Cost of €39.5 million. 30/02.
Open call for bids, deadline 19th September, 2002 for construction of the 2.9 km Sant Llorenç d'Hortons-Sant Esteve Sesrovires section in Barcelona. Includes four tunnels totalling 2,083 metres. Tender value €39.5 million. Visit http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=en&docid=124681-2002, OJ S 156, or contact GIF, Madrid, fax +34 913198535. 34/02.
Open call for bids, deadline 7th October, 2002 for construction of 2.1 km L'Hospitalet-Can Tunis section between Martorell and Barcelona, for access of both Spanish gauge and international gauge trains to the Barcelona harbour and the Can Tunis freight station. Includes a double-track tunnel. Value €96.5 million. Visit http://ted.eur-op.eu.int/udl?request=Seek-Deliver&language=en&docid=124688-2002, OJ S 156, or contact GIF, Madrid, fax +34 913198535. 35/02.
OHL
has been awarded the construction of the Sant Llorenç d´Hortons-Sant
Esteve Sesrovires section in Barcelona for €35 million and a time frame
of 13 ½ months. There will be four tunnel totalling 2,083 metres. Visit
www.gif.es 47/02.
FCC and Comsa have won the contract for the LHospitalet-Can Tunis stretch.
A 1,430 m double-track tunnel is required. Contract value €62 million.
47/02.
Open call for bids, deadline 23rd February, 2004 for reinforcement of the Lilla tunnel on section Lleida-Martorell in Catalonia. Budget: 53.9 million euros. Time frame: 10 months. Work will consist in reinforcing the lining and strengthening the invert. Cracks, craters and other abnormalities appeared in the tunnel due to the expansive ground comprising argilite and gypsum-bearing lutite with high contents of anhydrite. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=004002-2004, OJ S 5, or contact GIF, Madrid, fax +34 913198535. Read E-News Weekly 47/2003 & 11/2003. 03/04.
Open
call for tenders, deadline 23th February, 2004 for reinforcement of the Camp
Magré and Puig Cabrer tunnels on section Lleida-Martorell in Catalonia. Budget:
EUR26.2 million. Time frame: seven months. Work will consist in reinforcing
the lining and strengthening the invert. Cracks, craters and other abnormalities
appeared in the tunnel due to the expansive ground comprising argilite and
gypsum-bearing lutite with high contents of anhydrite. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=006500-2004,
OJ S 8, or contact GIF, Madrid, fax +34 913198535. 04/04.
Open call for tenders, deadline 4th February, 2004 for work control and management
during reinforcement of the Camp Magré and Puig Cabrer tunnels, section Lleida-Martorell
of the Madrid-Barcelona high speed link. Budget: EUR1 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=005099-2004,
OJ S 6, or contact GIF, Madrid, fax +34 913198535. Read E-News
Weekly 47/2003 & 11/2003.
04/04.
Open call for bids, deadline 12th March, 2004 for design and work supervision of the high speed rail tunnels in Girona and Sarrià, approximate lengths of 4 km for the IUC gauge line and 4.8 km for the Spanish gauge line, and the Girona station. Tender budget:EUR8 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=024978-2004, OJ S 28, or contact GIF, Madrid, fax +34 913198535. Read E-News Weekly 9/2002. 09/04.
Getinsa and Geocontrol won a EUR632,400 contract for work control and management during reinforcement of the 2,065 m-long 90 sq m Lilla tunnel, the 984 m-long 110 sq m Camp Magre tunnel and the 704 m-long 113 sq m Puig Cabrer tunnel, section Lleida-Martorell of the Madrid-Barcelona high speed link. Visit www.getinsa.es y www.geocontrol.es 16/04.
Ferrovial-Agroman has pocketed a EUR41.2 million contract for reinforcement works of the walls and invert of the 2,065 m x 90 sq m Lilla tunnel between Lleida and Barcelona. Visit www.ferrovial.es 17/04.
Corsan-Corviam has pocketed a EUR19.7 million contract for reinforcement works of the lining and invert in the 984 m 110 sq m Camp Magre tunnel and the 704 m 113 sq m Puig Cabrer tunnel on section Lleida-Martorell. Visit www.corsan-corviam.es 18/04.
Iberinsa and AEPO have secured a EUR4.9 million contract for design and work supervision of the high speed rail tunnels in Girona and Sarria, approximate lengths of 4 km for the IUC gauge line and 4.8 km for the Spanish gauge line, and the Girona station. Visit www.iberinsa.es and www.aepo.es 31-32/04.
Typsa has secured a EUR2.9 million contract for the design of the Sant Julia de Ramis-Pontos subsection on the Girona-Figueras section on the high speed line between Barcelona and the French border. This 16 km subsection includes five tunnels for a total length of 8,315 m, whereof two of 2.8 km and one of 1,550 m. Visit www.typsa.es 45/04.
Open
call for tenders, deadline 23rd february, 2005 for construction of the 4.1
km Sant Joan Despi-Sant Boi de Llobregat section in Barcelona. This section
includes a 2,356 m tunnel. Tender estimate: EUR88.3 million. Time frame for
construction is 21 months. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=012024-2005,
OJ S 13, or contact Administrador de Infraestructuras Ferroviarias (ADIF),
Madrid, fax +34 917005771. 04/05.
Open call for tenders, deadline 23rd february, 2005 for construction of the
2.7 km Hospitalet-La Torrassa section in Barcelona. This section includes
a 2,163 m tunnel. Tender estimate: EUR122 million. Time frame for construction
is 22 months. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=012033-2005,
OJ S 13, or contact Administrador de Infraestructuras Ferroviarias (ADIF),
Madrid, fax +34 917005771. 04/05.
Open call for tenders, deadline 23rd february, 2005 for construction of the
2.1 km La Torrassa-Sants section in Barcelona. This section includes a 1.8
km tunnel. Tender estimate: EUR106 million. Time frame for construction is
24 months. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=012027-2005,
OJ S 13, or contact Administrador de Infraestructuras Ferroviarias (ADIF),
Madrid, fax +34 917005771. 04/05.
The
ministry of public works awarded the construction contracts for the three
most critical high speed rail sections to access to Barcelona, located between
Sant Joan Despi and Sants station, worth a total amount of EUR275.7 million.
High speed trains will arrive in Sants in April 2007, if the project meets
the time frame. Section La Torrassa-Sants, which runs in majority in tunnel,
has been awarded to Sacyr, Scrinser and Cavosa for EUR79 million. This 2.1
km section includes a 1.8 km tunnel. The contractors committed to building
the section in 23 months and a half, not included the month necessary to sign
the contract. Visit www.sacyr.com
and www.cavosa.es 15/05.
Section Sant Joan Despi-Sant Boi, 4.1 km in length, has been awarded to Necso
for EUR66 million and a time frame to complete the job of 19 months. This
section includes a 2,356 m tunnel. Visit www.necso.es
15/05.
Section L'Hospitalet-La Torrassa, worth EUR92.8 million with a time frame
of 20 months, has been awarded to OHL and Agrupacion Guinovart Obras y Servicios
Hispania. This 2.7 km section includes a 2,163 m tunnel. Visit www.ohl.es
and www.guinoshsa.com
15/05.
Open call for bids, deadline 23rd May, 2005 for consulting and assistance for the follow-up, planning management and progress of the Madrid-Saragossa-Barcelona-French border line and coordination of works in Barcelona and its urban area. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=061900-2005, OJ S 64, or contact ADIF, Madrid, fax +34 917005751. 16/05.
Open call for tenders, deadline 28th June, 2005 for consulting and assistance aiming at reinforcing safety during construction of the access tunnels to Sants station in Barcelona and La Roca-Ruidellots section on the Madrid-Saragossa-Barcelona-French border high speed line. The assignment consists in following up the project and proposing improvements to safety measures to avoid any accidents or collapse in the tunnels and their consequences for the construction itself and the neighbouring facilities and buildings, working in coordination with the planning control teams and supporting these teams with regard to tunnelling safety. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=088720-2005, OJ S 90, or contact ADIF, Madrid, fax +34 917005751. 21/05.
Euroconsult secured a EUR534,000 contract for consulting and assistance to reinforce safety during construction of the access tunnels to Sants station in Barcelona and La Roca-Ruidellots section on the Madrid-Saragossa-Barcelona-French border high speed line. Click es/20. Visit www.euroconsult.es 36/05.
Open call for tenders, deadline 12th December, 2005 for safety and health coordination during the construction of section Vila Franca del Penedes-Barcelona on the Madrid-Lleida-Barcelona-French border high speed line. Conéctese a http://ted.publications.eu.int/udl?request=Seek-Deliver&language=es&docid=217522-2005, DO S 220, o contáctese con el ADIF, Madrid, fax +34 917005771. 48/05.
Open call for tenders, deadline 29th May, 2006 for inspection of buildings near the tunnel works between Sants and La Sagrera in Barcelona, which is the city access of the Madrid-Saragossa-Barcelona-French border line. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=079310-2006, OJ S 75, or contact ADIF, Madrid, fax +34 917005751. 17/06.
Intemac won a EUR1 million contract to inspect buildings near the tunnel works on the Sants-La Sagrera section in Barcelona, which is the central city access of the Madrid-Saragossa-Barcelona-French border line. Visit www.intemac.es 36/06.
Open
call for tenders, deadline 13th November, 2006 for construction of the Sant
Julia de Ramis-Cornella del Terri section on the Madrid-Saragossa-Barcelona-French
border high speed line in Girona province. This 3.3 km section includes two
mined tunnels: La Garriga, 758 m and Sant Andreu, 649 m. Both tunnels will
have a cross section of 110 sq m. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=210172-2006,
OJ S 198, or contact ADIF, Madrid, fax +34 917005751. 43/06.
Open call for tenders, deadline 13th November, 2006 for construction of the
Cornella del Terri-Vilademuls section on the Madrid-Saragossa-Barcelona-French
border high speed line in Girona province. This 7.1 km section includes two
mined tunnels: Llogaia, 1,713 m and Feixes den Vidal, 1,372 m. Both tunnels
will have a cross section of 90 sq m. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=209095-2006,
OJ S 197, or contact ADIF, Madrid, fax +34 917005751. 43/06.
Open call for tenders, deadline 13th November, 2006 for construction of the
Vilademuls-Pontos section on the Madrid-Saragossa-Barcelona-French border
high speed line in Girona province. This 5.66 km section includes one mined
tunnel in Les Cavorques, 2,939 m and 85 sq m of cross section. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=210176-2006,
OJ S 198, or contact ADIF, Madrid, fax +34 917005751. 43/06.
Open
call for tenders, deadline 11th December, 2006 for construction of the Trinidad
junction-Monteada section on the Madrid-Saragossa-Barcelona-French border
high speed line. The 4.75 km section includes a 3,709 m-long tunnel, whereof
2,900 metres will be bored by an 11,300 mm-outer diameter TBM. The cross section
will be 64.77 sq m. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=229310-2006,
OJ S 208, or contact ADIF, Madrid, fax +34 917005751. 47/06.
Open call for tenders, deadline 2nd January, 2007 for work control during
construction of the Mollet del Valles-Montomes del Valles y Montomes del Valles-La
Roca del Valles sections on the Madrid-Saragossa-Barcelona-French border high
speed line. These sections are 3.4 km and 10.2 km long and include five cut-and-cover
tunnels of 1,220 m, 616 m, 146 m, 469 m and 658 m. The Barcelona-Port Bou
line in Montmelo will also be sunk underground. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=230920-2006,
OJ S 215, or contact ADIF, Madrid, fax +34 917005751. 47/06.
Open call for tenders, deadline 2nd January, 2007 for work control during
construction of the Sant Julia de Ramis-Pontos section on the Madrid-Saragossa-Barcelona-French
border high speed line. This is the reunion of three sections of 3.3 km, 5.7
km and 5.7 km, including five tunnels of 758 m, 649 m, 1,713 m, 1,372 m and
2,938 m. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=230919-2006,
OJ S 215, or contact ADIF, Madrid, fax +34 917005751. 47/06.
Open
call for tenders, deadline 5th February, 2007 for construction of the 10.3
km-long Montornes del Valles-La Roca del Valles section. Construction will
take 21 months. This section includes four cut-and-cover tunnels of 616 m,
146 m, 469 m and 658 metres respectively. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=4099-2007,
OJ S 4, or contact ADIF, Madrid, fax +34 917005751. 03/07.
Coprosa secured a EUR46
million contract to build the 3.3 km-long Sant Julia de Ramis-Cornella del
Terri section in Girona province. Construction will take 18 months. This section
includes the 758 m-long Garriga tunnel and the 649 m-long Sant Andreu tunnel.
Visit www.coprosa.es 03/07.
A JV formed by Sacyr and its subsidiaries Cavosa and Scrinser signed a EUR93.2
million deal to build the 7.1 km-long Cornella del Terri-Vilademuls section,
in Girona province. Construction will take 17.5 months. This section includes
the 1,713 m-long Santa Llogaia tunnel and the 1,372 m-long Feixes d'en Vidal
tunnel. Visit www.sacyr.com
or www.gruposyv.com
and www.cavosa.es 03/07.
A EUR85.1 million contract has been awarded to a JV of FCC and Servia Canto
to build the 5.66 km-long Vilademuls-Pontos section, in Girona province. Construction
will take 19.5 months. This section includes the 2,939 m-long Les Cavorques
tunnel. Visit www.fcc.es and
www.servia-canto.com
03/07.
Open
call for tenders, deadline 5th February, 2007 for construction of the 3.3
km-long Mollet del Valles-Montornes del Valles section. This section includes
a 1,220 m-long cut-and-cover tunnel and an underground station in Montmelo.
Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=5110-2007,
OJ S 5, or contact ADIF, Madrid, fax +34 917005751. 04/07.
Construction of the 4.75 km Trinidad junction-Montcada i Reixac section on
the Madrid-Saragossa-Barcelona-French border high speed line has been commissioned
to Corsan-Corviam, Copasa, and Vias y Construcciones. The contract is worth
EUR127.6 million. The section includes a 3,709 m-long tunnel, whereof 2,900
metres will be bored by an 11.3 m-diameter TBM. Visit www.corsan-corviam.es,
www.copasa.es and www.vias.es
12/07.
The contract for construction of the 3.3 km-long Mollet del Valles-Montornes
del Valles section has been awarded to a JV of Ferrovial Agromán and
Compañía de Obras Castillejos for EUR105.5 million and a time
frame of 30 months. The most important structure is a 1,220 m-long cut-and-cover
tunnel in Montmelo through which the new IUC gauge trains and the existing
Spanish gauge trains will run. Visit www.ferrovial.es
15/07.
The contract for construction of the 10.3 km-long Montornes del Valles-La
Roca del Valles section has been awarded to a JV of Aldesa Construcciones
and Construcciones Pai for EUR61.8 million and a time frame of 19 months.
This section includes four cut-and-cover tunnels of 616 m, 146 m, 469 m and
658 metres. Visit www.aldesaconstrucciones.es
15/07.
Geocisa and Typsa received a EUR2.7 million contract for work supervision
during construction of the 17.7 km Mollet del Valles-Montornes del Valles-La
Roca del Valles section. Visit www.geocisa.com
and www.typsa.es 15/07.
Open
call for tenders, deadline 7th June, 2007 for inspection of buildings near
the tunnels of the Trinidad junction-Monteada section in Barcelona. The 4.75
km section includes a 3,709 m-long tunnel, whereof 2,900 metres will be bored
by an 11,300 mm-outer diameter TBM. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=98211-2007,
OJ S 80, or contact ADIF, Madrid, fax +34 917005751. 19/07.
Open call for tenders, deadline 19th July, 2007 for construction of the 7.5
km Borrassa-Figueres section in Girona province, including a 1,750 m tunnel.
Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=139226-2007,
OJ S 113, or contact ADIF, Madrid, fax +34 917005751. 25/07.
Open
call for tenders, deadline 16th August, 2007 for construction of the urban
tunnels and first phase of the station in Girona. The 3.6 km section includes
two TBM-built tunnels of 1,297 metres and 1,564 metres, featuring an outer
diameter of 11.75 metres and cross-section of 69 square metres, named Girona
I and Girona II. The 1,564 m-long Girona II tunnel will connect with the next
section, the 3,042 m-long Sarria tunnel, so that trains will travel through
a 4,606 m-long tunnel altogether. The contract also includes the first phase
of the new intermodal station. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=161971-2007,
OJ S 132, or contact ADIF, Madrid, fax +34 917005751. 29/07.
Open call for tenders, deadline 16th August, 2007 for construction of the
5 km Sarria de Ter-Sant Julia de Ramis section, which includes two tunnels
to be excavated by traditional method. The first tunnel, the 3,042 m-long
Sarria tunnel, will connect to the previous section, the 1,564 m-long Girona
II tunnel, so that trains will travel through a 4,606 m-long tunnel altogether.
The second tunnel, the Montagut tunnel, is 475 m long. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=161950-2007,
OJ S 132, or contact ADIF, Madrid, fax +34 917005751. 29/07.
Open call for bids, deadline 3rd September, 2007 for construction of the 5.6 km Sants-La Sagrera tunnel section in Barcelona. The first 422 metres an