![]() |
Buenos Aires - ar/15
Water Supply
15 km-long, 3.5 m-diameter Saavedra-Moron tunnel reaching completion by Wayss & Freytag/Sollazo Hnos for Aguas Argentinas using Herrenknecht EPB. Safege Montgomery Watson are clients engineer. Tunnelling conditions post-evaluation study carried out by team chaired by Mike Kobler of Underground Construction Managers and including Alastair Biggart of Hatch Mott MacDonald and Gary Brierley of Brierley Associates. Visit www.brierleyassociates.com January 2000.
Completion
of $65 million Saavedra-Moron reported. The tunnel comprises four drives of
3.56 km, 4.2 km, 3.7 km, and 3.8 km at depth 35 m from five shafts. Ground conditions
were variable, ranging from quicksands under 2.5 bar pressure, through green
sandy clays to hard consolidated silts with calcareous nodules. Soil conditioning
using bentonite or foam, or both. The two Herrenknecht 4.3 m-diameter EPBs averaged
20 x 1.2 m-wide gasketed rings/day with a best performance of 35 rings. Visit
www.herrenknecht.com
March 2000.
China
Guangzhou - cn/16
Metro
18.5 km from Xilang to East Station to be commissioned June, 1999 at final cost of $US1.53 billion. April 1999.
Construction of 21.34 km-long section of Metro Line 2 commenced in July, 1998 for completion 2003 at a cost of $1.2 billion. Undergoing feasibility studies is Suburban LRT Line with a total length of 26 km. Contact Director, Guangzhou Preparatory Office of Underground Railroad, No 204 Huanshi Road, Guangzhou, China 510010. November 1999.
Work commenced on 23.3 km-long Line 2 with 22 stations at projected cost of $1.3 billion. Phase 1 being undertaken by Shanghai Tunnel Shareholding Company involves TBM boring 190 m-long connection under Pearl river from Haihu Square station site for completion in 2002. Project commissioning scheduled for 2004. May 2000.
Two
new lots awarded this year: north tunnel to Ministry of Railways Tunnel Bureau
with two new Herrenknecht TBMs; and south tunnel to Guangzhou Municipal Dunjian
Underground Construction Engineering Co.,Ltd who have purchased two Herrenknecht
machines from the North East Line in Singapore. Each of the four machines will
bore approx. 2 km in weathered mudstone/claystone up to 60 Mpa with some clay
areas. The machines have VMT guidance and are EPB with hard rock features including
cutters, powerful drive, stabilisers and optional semi-open or open mode. Segments
are 1.5 m long, 5 + 1 (left and right), outside diameter 6.0 m, inside 5.4 m.
The moulds & segment design by Ceresola AG. Visit www.ceresola.com
and www.herrenknecht.com
October 2000.
Subway Corporation of Guangzhou City has submitted feasibility study for a high-capacity, 120 km/h third line to commence construction end-2001. Second 80 km/h line currently under construction at 23.27 km-long will be operational in 2003. Fourth line in preliminary design. Visit www.herrenknecht.de December 2000.
Fourth subway planned 17.7 km to Bazhou and fifth from Guangzhou Baiyun Airport 35.3 km to Guangzhou East Railway Station. To date, five stations on the second subway, Jiangxia 23.265 km to Bazhou, have been excavated. Detailed plans for third subway, from Guangzhou East Railway Station 32 km to Panyu District, have been submitted to the State Development Planning Commission. Visit www.xinhua.cn 15/01.
Construction of 8.55 km-long experimental section of third metro line, crossing Pearl River twice and with five stations, to start late-2001. 35.75 km-long third line from Guangzhou East Railway Station to Panyu District will be Y-shaped and have 18 stations. Completion is planned for 2007 at $1.92 billion. Visit www.xinhua.cn 24/01.
Government approval for line
3 with 18 stations over 35.75 km length. The main line will run from Guangzhou
east railway station to the Fanyu Square with 13 stops. Extension line from
Tianhe bus stop to East Tianhe Street will have five stops. Construction of
8.5 km-long experimental line to start end-2001. Visit www.xinhua.cn
32/01.
China
Beijing - cn/28
Metro
13.5 km eastern extension of Line 1 along Chang’an Street between Xidan and Bawangfen which has been under construction since 1996 should be completed by May, 2000 at a cost of $0.9 billion. Test operations underway on 10.7 km section between West Tian’anmen Square and Sihui and work proceeding on section between Tian’anmen Square and Xidan. Westside South-North Line with total length of 19.5 km under feasibility study. Contact Gao Yucai, MD, Beijing Mass Transit Railway Corporation, No 2 Beiheyan Road, Xicheng District, Beijing, China 100044, tel +86 10 832 0560, fax 832 0077. November 1999.
Metro line 5 will be constructed by Beijing Underground
Construction Group Pte Ltd using new 6.2 m-diameter Herrenknecht EPB value $5
million. Visit www.herrenknecht.com
May 2000.
Five sections of Line 5 from Dongdan north to Yonghegong will be constructed by Beijing Underground Construction Group using a new Herrenknecht 6.2 m-diameter EPB scheduled for delivery November, 2000. Lining will comprise six-piece 1.2 m-wide segmental concrete rings with i.d. 5.4 m. The first job in January, 2001 will be a test tunnel from Beixinqiao to Yonghegong in Quaternary clayey soil with sand, gravel and silt with 25 mm maximum particle size where the water table is at 6 m to 10 m below surface level. Visit www.herrenknecht.com June 2000.
Beijing No 5 Subway Line Investment Co Ltd, 37.5% owned by SNC-Lavalin, has secured $1.45 billion funding to start five-year construction of 27.6 km-long No 5 line. Final design approved for link between Songjiazhuang in Fengtai district in the south to Taipingzhuang in Changping district in the north, and 700 m-long test section is under construction. Visit www.snc-lavalin.com and www.herrenknecht.com 18/01.
Herrenknecht reports 6.2 m EPB launch from shaft at Lama Temple for 680 m drive to Beixinqiao Station at an average depth of 20 m in silty clays, fine sands and gravels with maximum water table 10 m above crown. First 60 m completed using screw conveyor to skips, then backup taken underground and connected. Precast concrete ring with straight, right and left segments, 1.2 m-long and 300 mm-thick. Average 2 rings/12h-day, max 3 rings during launch. Non-cement grout pumped from surface to tailskin. Herrenknecht responsible for first 100 m of excavation including site set-up, settlement control, ring quality and training. Visit www.herrenknecht.com 31/01.
Construction of No. 13 subway line between Beijing urban ring and international airport announced at 5th Beijing-Hong Kong Economic Co-operation Symposium. Line will be 18.15 km-long with 1.63 km at grade, 12.82 km elevated, and 3.7 km underground, and will start driving north-east at Wangjingxi station and have nine stations. Cost estimated at 4.3 billion yuan for construction between January, 2002 and December, 2004. Overseas investment invited. Visit www.xinhua.net 45/01.
Beijing Construction Engineering Co. Ltd. and Bilfinger+Berger are to invest a further US$9 million in their jv Chang Cheng Bilfinger Berger Construction Engineering Corp. Ltd. to lobby for the construction of Beijing's No. 5 subway line. The north-south 27.7 km No. 5 metro line is urgently needed by Beijing as it will be the main artery between the city's southern areas and its north, where the Olympic Games village will be located. 10/02.
Plans have been approved for Line 10 of the Beijing Metro and construction work is expected to begin at the end of this year. Phase one, which also includes the Olympic Extension, will run largely underground. It will be 24.59 km-long with 22 underground stations while the Olympic Extension will be 5.91 km long and have four underground stations. Altogether, the 33 km line will have 28 stations, of which 27 stations will be constructed underground. Line 10 will pass through the Central Business District and will intersect with Lines 1, 4 and 5 and the City Rail Line System. Tenders for various engineering and civil work contracts are being invited and completion is scheduled before the Beijing Olympic Games in 2008. The total investment is estimated at US$873.25 million. 45/03.
MTR Corporation, Hong Kong's metro operator, has entered into a Memorandum of Understanding (MOU) with Beijing Infrastructure Investment Co. Ltd and Beijing Capital Group to form a Public-Private Partnership (PPP) for construction and operation of Line 4. The total investment for metro line 4 is about USD1.9 billion. The 28.65 km line is underground, running from south of the fourth ring road at Majialou Station to north of the Summer Xuan Sun Wu, Xi Cheng and Hai Dian Districts. It will be Beijing's main north-south traffic artery and one of the major infrastructure projects for the 2008 Olympic Games. Visit www.mtr.com.hk 20/04.
Bernold-Ceresola has been awarded the contract to supply six sets of 6,000 mm stationary moulds by Beijing Ruibo Cement Products for the concrete segments of the Beijing metro line 4. Visit www.bernold-ceresola.com 21/04.
The
Beijing metro Olympic extension construction contract has been awarded to a
joint venture comprising China Railway Engineering Company, China Railway Electrify
Bureau Group Company and China Railway Third Bureau Group Company. The BOT contract
is valued at USD133.53 million.
The Olympic extension on Line 10 will be 4.34 km long and the entire line will
run underground. There will be four stations and it will be the only metro line
reaching the central area of the Olympic Park. Completion is scheduled for June
2008. 25/05.
Colombia
Bogota - co/13
Sewer
Soletanche undertaking 10 km of pipejacking using two Herrenknecht machines of 2.6 m and 2.25 m diameter. December 1999.
Egypt
Cairo - eg/11
Highway
Al Azhar
Two road tunnels costing $120 million using Herrenknecht Mixshield. Contractor: jv of Campenon Bernard/SGE with Bouyges, Dumez, GTM, Spie Batignolles and Arab Contractors. June 1998.
Two-lane tunnel with two tubes of 2.5 km built by Arab Contractors, Campenon Bernard, Eiffage, and Spie, inaugurated on 28th October, 2001. Equipped with anti-fire walls and slide access every 100 metres to an emergency gallery under the carriageway. 45/01.
France
Reunion - fr/13
Water Transfer
Salazie
9.5 km TBM drive awarded to jv of Spie Batignolles, Sotrabas, Razel-Pico and Bilfinger & Berger. Second drive of 8.4 km due for award. March 1998.
Two tunnels, the 8 km Galerie Salazie Amont from the Mat river to the Pluis river and the 9.65 km x 3.2 m-diameter Galerie Salazie Aval from the Pluis river to the Fleurs-Jaunes river will allow transfer of water from the east of the island to the west. The Amont is being driven by a jv led by Bouygues and the Aval by a jv led by Spie Batignolles, both of which include Razel, Pico, Sotrabas, and Bilfinger & Berger. Two Herrenknecht TBMs are in use in basalts and similar volcanic rocks with maximum cover of 1,000 m. Fax M Coulet of Razel/Pico in Reunion, +262 44 9820 for progress and visit www.herrenknecht.com for further details of the TBM specifications. February 2000.
France
Paris - fr/21
Orbital Motorway
Possible tunnels for commencement 2001: Sinard south to Grenoble on autoroute A51; Lodeve on route nationale RN75. SGE, GTM and Eiffage to start work on A86 highway tunnel using Cofiroute TBM end-1999. Sept 1999.
Socatop, a jv which comprises Campenon Bernard, GTM, Colas, Eiffage, and Jean
Lefebvre, has started construction of the 4.5 km-long first section of the A86
east tunnel from Rueil to the A13 in sands, chalk, limestone and clay using
its 11.6 m-diameter Herrenknecht Mixshield. Tunnel will be segmentally lined
at 10.4 m internal diameter and will accommodate three lanes of light traffic
in each direction on two levels. Second 5.6 km-long section from A13 to Versailles
will commence in 2004, and 7.6 km-long x 10.9 m i.d. west tunnel in 2005. For
equipment details visit www.herrenknecht.de
and for a pleasurable experience visit www.eiffage.fr
December 2000.
A JV of SEITHA and Clemessy has secured a contract to equip with Zitron fans the east tunnel on the A86 highway west of Paris. There will be approximately 200 fans, power ranging from 22 to 500 kW. Visit www.seitha.fr, www.clemessy.fr and www.zitron.com 30/05.
Germany
Lübeck
- de/11
Highway
River Trave tunnel 900 m-long at cost of DM 300 million to be driven by jv of Hochtief and Bilfinger & Berger for commissioning 2005. 30-year concession. February 1999.
Toll tunnel 1 km-long under River Trave awarded to jv of Hochtief and Bilfinger & Berger value $154 million. Land acquisition survey completed. Construction will commence in 2001 and last four years. October 1999.
$160
million finance for Herren tunnel will be on BOT basis. It becomes the first
toll route in Germany, with a 30 years handover. Federal government is contributing
more than half of the cost as the difference between that of bridge and tunnel.
October 1999.
Herrentunnel Lubeck GmbH has been formed by Hochtief and Bilfinger & Berger
to plan, construct, finance and operate the twin-tube, 11.5 m o.d., 10.5 m i.d.,
1.04 km-long tunnel which will be 9.5 m below the riverbed. A shield will be
used for 780 m and the remaining 260 m will be cut-and-cover, with 600 m of
ramps. There will be two crosspassages for emergency use. Construction to commence
Spring, 2001 for opening 2005. Visit www.bilfingerberger.de
Sept 2000.
Schleswig Holstein regional government has approved 1 km-long, twin-tube Herren tunnel for Lubeck municipality for construction start in 2002 by Hochtief/Bilfinger & Berger subsidiary. Visit www.hochtief.de 14/01.
Preparatory works of the Herren tunnel under river Trave in Lübeck started in October, 2001. The tunnel has two 750 m tubes connected by two cross passages. It will be built under DBFO by a joint company of Hochtief and Bilfinger+Berger. Tunnelling to start at summer 2002 using a overhauled Herrenknecht hydroshield machine used to bore a tunnel under the Weser river in Bremen. Visit www.herrentunnel.de 05/02.
Germany
Nuremberg - de/20
Sewer
Pipejack
Construction of 1.31 km-long, 2.5 m-diameter section of southwest sewer awarded to Wuwa Bau at value $7.2 million. Will be bored early-2000 by a Herrenknecht shield which is currently completing another stretch. October 1999.
Germany
Bremen - de/25
Highway
Wesser, near Bremen, twin highway tunnel 2 x 1.6 km using 11.67 m-diameter Herrenknecht Mixshield S-152. Contractors Hochtief AG, Philipp Holzmann AG, Ludwig Freytag GmbH, Heinrich Hecker GmbH and Martin Oetken GmbH. November 1999.
11.7 m-diameter Herrenknecht Mixshield has completed 1.3 km with 300 m to go
on south tube. Will be dismantled and taken back across Weser for relaunch for
north tube after planned modification to cutterhead to improve bentonite flow
through integral rock crusher. Ground conditions are sand, clay, gravel and
boulders up to 1 m diameter. 140,000 t of Norwegian granite of 150 mm nominal
sizing placed as carpet over 500 m-long x 75 m-wide section of riverbed as protection
against blowout and tunnel elevation has been deepened by 3.5 m. The 30% of
cutters visible above the lowered bentonite level have been changed twice by
divers, but slower progress is presently more acceptable than further cutter
changes at up to 4.5 bar. Segmental lining outside diameter 11.3 m and 50 cm
thick with 1.5 m width. Weight of 6+1 ring is 65 t. Average advance 3 rings/day
in clay and 10 rings/day in sand. Overall average 4.2 m/day with 16 m maximum.
Visit www.herrenknecht.com
October 2000.
Hochtief reported successful breakthrough of its 11.7 m-diameter Herrenknecht slurry TBM on the south tube of the Weser crossing north of Bremen on Tuesday 14th November, 2000 after a difficult drive in which great precaution was taken to avoid blowout through the riverbed. The holing was "inch-perfect", thanks mainly to expert operation of the VMT guidance system. The TBM will now be dismantled and transported across the river for assembly and relaunch on the north tube. For further details visit www.hochtief.de or www.herrenknecht.com November 2000.
North tube of Weser tunnel got underway on 26th February, 2001 following three months TBM recommissioning. The machine was officially relaunched by Niedersachsen´s tunnel godmother, Dr Birgit Grote. With seven-day working, this second tube should hole through by end-2001. Visit www.hochtief.de and www.herrenknecht.com 09/01.
Negotiated procedure, deadline 16th March, 2004 for engineering services for section 4 Hafenrandstrasse-Strom (4.2 km) of motorway A281 including the 2 x 1.6 km Weser tunnel. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=028329-2004, OJ S 32, or contact GPV Bremer, Bremen, fax +49 4213303877. 11/04.
Negotiated procedure, deadline 6th April, 2004 for design engineering for a 1.4 km immersed tube tunnel under the Weser river on section 4 Hafenrandstrasse-Strom of the A281 motorway. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=041419-2004, OJ S 48, or contact GPV Bremer Gessellschaft, Bremen, fax +49 4213303877. 12/04.
Negotiated
procedure, deadline 30th April, 2004 for engineering services for a 4.2 km section
of motorway A281, including a 1.4 km tunnel crossing of the Weser river. Visit
http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=053220-2004,
OJ S 62, or contact GPV Bremer Gesellschaft, Bremen, fax +49 4213303877. 15/04.
Germany
Hamburg - de/29
Highway
The 2.56 km-long fourth Elbe tunnel broke through safely on 1st March, 2000 after a harrowing 29 month drive. The 14.2 m-diameter Herrenknecht Mixshield, the largest ever built, worked at up to 14 m/day through extremely complex ground comprising gravel, granite blocks, sand, silt, tillite and mica silt under pressures of 5 bar with minimum cover of 7 m to the riverbed. A stonecrusher positioned behind the cutting wheel dealt with boulders up to 1.2 m-diameter, while an integrated active centre cutter with a diameter of 3 m located in the middle of the cutting wheel was able to drill independently up to 0.6 m ahead to prevent adhesion. Acoustic reflection measurements detected geological changes up to 40 m ahead of the machine. The 2,600 t, 3,200 kW machine will now be refurbished for a 3.2 km-long city motorway tunnel in Moscow. More from www.herrenknecht.com March 2000.
Open invitation to tender, deadline 8th April, 2004 for core drills and ground investigation as part of a new Elbe river crossing in tunnel on the northwest bypass in Hamburg on highway A20. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=044535-2004, OJ S 52, or contact Straßenbauamt Itzehoe, Itzehoe, fax +49 4821662714. 13/04.
Open invitation to tender, deadline 23rd August, 2004 for core drills and ground investigation as part of a new Elbe river crossing in tunnel on the northwest bypass in Hamburg on highway A20. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=118852-2004, OJ S 139, or contact Straßenbauamt Itzehoe, Itzehoe, fax +49 4821662714. 31-32/04.
Open invitation to tender, deadline 29th September, 2004 for drainage works as part of the rehabilitation of the first tube of the Elbe tunnel. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=150709-2004, OJ S 176, or contact Behorde fur Stadtentwicklung und Umwelt, Hamburg, fax +49 40428402641. E-mail dietmar.gehrt@bsu.hamburg.de or christoph.vater@bsu.hamburg.de 38/04.
Open call for tenders, deadline 8th March, 2005 for execution of 24 core drills in the Elbe at 70 m under the water and testing plus 12 penetration testing in the Elbe, as part of the new Elbe crossing on the A20 northwest bypass. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=010391-2005, OJ S 11, or contact Landesbetrieb Strassenbau und Verkher Schleswig-Holstein, Itzehoe, fax +49 4821662714. 04/05.
Negotiated procedure, 6th May, 2005 for project planning and design of the A20, northwest bypass in Hamburg, on its section running from the A20/K28 connection in east Drochtersen in Lower Saxony to the A20 / B431 in south Glueckstadt in Schleswig-Holstein nearby the Elbe tunnel crossing. The route section has a length of approx. 10.4 km, whereof approx. 6 km of tunnel. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=064984-2005, OJ S 67, or contact Landesbetrieb Strassenbau und Verkher S-H, Itzehoe, tel+ 49 4821662602 or 2632 or 2681. 15/05.
Open call for tenders, deadline 23rd May, 2005 for exploration drilling for the new Elbe tunnel crossing on the A20 highway bypass. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=066437-2005, OJ S 69, or contact Landesbetrieb Straßenbau und Verkher Schleswig-Holstein, Itzehoe, fax +49 4821662714. 16/05.
Negotiated procedure, deadline 21st November, 2005 for the draft design of the new Elb crossing for the A 20 northwest bypass in Hamburg, section from the K 28 in Lower Saxony to the B 431 in Schleswig-Holstein. It will be presumably a two-tube tunnel in loose material, built by TBM. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=200805-2005, OJ S 203, or contact Landesbetrieb Straßenbau und Verkehr Schleswig-Holstein, Itzehoe, fax +49 4821662714. 43/05.
Elbe-Link Ingenieurgemeinschaft, a joint venture of IMS Ingenieurgesellschaft, Spiekerman, Boeger + Jaeckle and Babendererde Ingenieure, received a EUR1.3 million contract for the feasibility study of the northwest bypass of the A 20 in Hamburg, from the K 28 (Lower Saxony) to the B 431 (Schleswig-Holstein), including a possible Elb crossing in tunnel. The assignment encompasses the alternatives for length, construction method, planning of all engineering work, technical equipment, the production of a draft for the preferred variant, etc. Visit www.ims-ing.de, www.spiekermann.de, www.boeger-jaeckle.de and www.bab-ing.com 19/06.
India
Bombay - in/31
Sewage Transfer
Herrenknecht 3.1 m-diameter single-shield hardrock TBM delivered to jv HCC/McNally
for 2.3 km-long, 20 m-deep, segmentally-lined Ghatkopar high level tunnel in
weathered basalt where high water inflows are possible. Client: BMC/World Bank.
Engineer: Binnie & Partners (India), TCE Consulting Engineers. Segment moulds
from CBE. Visit www.hccindia.com
and www.herrenknecht.com
32/01.
Bangalore Mass Rapid Transit Ltd (BMRTL) is inviting expressions of interest, deadline 18th May, 2005 for general consultancy services for the Bangalore metro, Phase I consisting of two corridors (east-west and north-south). The first phase covers 33 km, whereof 26 km elevated and 7 km underground (3.4 km on the east-west line and 3.3 km on the north-south line). The estimated construction cost is USD900 million. The project will take five years to build. The scope of the services include, among other things, preliminary system design; tender design and tender documentation; bid process management and selection of designers, contractors and suppliers; review of detailed designs; construction supervision; quality, safety and environment management; contract management; testing and commissioning of the entire system. Contact Managing Director, Bangalore Mass Rapid Transit Ltd. (BMRTL), Unit 305, 3rd Floor, Blue Cross Chambers, No.11, Bhagwan Mahavir Road Cross, (Infantry Road Cross), Bangalore 560001. Tel. +91 80 25599324, 25599325 or 25591061, fax +91 80 25591699. Visit www.bmrtl.com/ExpressionGC.pdf. A prequalification notice of contractors for the elevated sections has also been published. Visit www.bmrtl.com/tendernew.htm. Subscribe to E-News Weekly 1/2003. 14/05.
Italy
Rome - it/15
Railway
EPB
Two 800m x 8m-diameter tunnels to be driven by EPB and one 300m by conventional methods for Italferr. December 1998.
$40 million. Joint venture of Alpine Bau, Coopsette and CCC to construct 1.9 km x 38.5 m2 segmentally-lined tunnel between Roma Trastevere and Roma St Peter stations on Viterbo line using EPB. Single bore of 7 m i.d. Quattro Venti underground station at halfway position included in the contract. August 1999.
Construction of $29 million, 2.2 km-long Quattro Venti single bore, twin-track tunnel awarded to Astaldi/Impregilo for July, 2001 start. Herrenknecht 7.9 m-diameter EPB will install precast segmental lining on drive from Trastevere to San Pietro in tuff, silt-clay alluvials, and gravel with 2-6 m cover and up to 3.5 bar water pressure. Visit www.rocksoil.com and www.herrenknecht.com 17/01.
Kuwait
Kuwait
City - kw/11
Sewers
Greenline (Lebanon) and Kuwaiti Brueckner Construction using numerous Herrenknecht
AVN machines from 500 mm to 1,200 mm to drive up to 1 km/month on different
projects. Contact through www.herrenknecht.com
April 2000.
Netherlands
Rotterdam-Germany - nl/11
Rail Freight
Betuwe Line
Slurry TBM
Three tunnels along 160 km alignment: Botlek, Sophia and Pannerdensch. Botlek is 1.74 km and is being built by BTC consortium using a Herrenknecht TBM. Sophia is 6 km and will be built by the Tubecon consortium. Clays and peaty layers under high water tables. Netherlands Railways Betuwe Management Group is the responsible authority through the offices of Rene Buvelot and Jan Jonker. Consultant: Professor Bernard Maidl, Ruhr University. Completion for 2005. March 1998.
Invitation to tender for design and construct of line south including tunnels. August 1999.
Contract award to jv of Heymans, Strukton, Boskalis and CFE for 22 km-long Papendrecht-Lingeval section of the Betuwe line from Rotterdam to Cologne value $220 million. Includes 1.4 km Giessen tunnel in cut-and-cover. November 1999.
Award of $160 million contract to Comol jv for 1.85 km-long, 8.65 m-diameter twin-tube tunnel on Betuwe line to cross beneath Pannerdensch canal and main Zevenaar railway lines for a start in April, 2000. Comol comprises Dumez-GTM, Campenon Bernard, TBI Betonen Waterbow, Welling Didam and CFE. January 2000.
The Betuwe line will be twin track throughout and parallels the A15 highway across Holland. It involves some 130 structures, which include five tunnels totalling 18 km in length. Total project cost estimated at $4.5 billion. Zevenaar tunnel near Emmerich will be 1.5 km-long cut-and-cover using sheet piling with underwater concrete. Giessen tunnel base will have to be supported on piles because of poor support characteristics of ground in this area. Currently in design to cross beneath small waterway. March 2000.
Consortium Comol led by Vinci allied with CFE, TBI Beton-en Waterbau and Welling started excavating beneath Pannerdensch Kanaal near Arnhem using Herrenknecht Mixshield from Cairo metro. Two 9.8 m-diameter bores of 1,600 m to be driven in tricky conditions consisting of sand and clay together with crossing of a dyke and a flooded sand quarry. Contract value is Euro160 million. Visit www.groupe-vinci.com and www.herrenknecht.com 42/01.
Netherlands
Westerschelde - nl/18
Marine Highway
Twin
tube 6.6 km-long undersea highway tunnel using two 11.3 m-diameter Herrenknecht
Mixshields from an artificial polder at Terneuzen on the south side to 20 m-deep
concrete caissons at Ellewoutsdijk on the north side. Face supported by water/bentonite
mix and all spoil is pumped to surface separation plant. Much of the tunnel
will be in the very dense Boom clay which varies in thickness between eight
and 38 m in the middle of the Schelde, but sand above and below this stratum
is of variable quality, sometimes containing glauconite. At deepest point tunnel
is 65 m below sea level, and machines are designed to work up to 8.5 bar. Two
pressure chambers on each TBM allow transfer of divers by transport capsule
from a pressurised habitat at surface to the face for continuous operations,
saturation diving over long periods if necessary. Interlocking gasketed lining
of 7 segments and key. 26 cross-passages planned at 250 m intervals where five-ring
special sections are being installed on advance and freezing will be necessary.
Service duct installed at floor level and invert backfilled on advance. Rear
160 m of TBM gantry supported by roller brackets installed to sidewall. Two
Schoma locos required on each material train to cope with 4.5% gradient at entrance
ramp. TBMs have advanced 600 m in east tube and 500 m in west tube. Contracting
jv KMW are to design, construct and maintain tunnel for first 10 years of operation.
Opening date March, 2003. Visit www.westerscheldetunnel.nl
for further information. February 2000.
The record-breaking saturation diving operation
conducted at 6.5 bar pressure to install 12 larger profile cutters on each of
the TBMs has been successful and both machines are boring again. The changeover
took six working days for each machine, and 11 days including decompression.
See Hall
of Fame entry or visit www.herrenknecht.com
August 2000.
KMW reports both TBMs 2 km into 6.6 km drives following recent installation of profile cutters by divers when excessive pressure in waterbearing sands caused distortion to shields. Now advancing at 14 rings/day in Boom clay without difficulty. Visit www.westerscheldetunnel.nl and www.herrenknecht.de December 2000.
The two Herrenknecht Mixshields excavating the Westerschelde tunnel are reported to break record after record. 'Sara', the machine boring the east tube, has recorded an advance of 32 metres in just 24 hours. Only 724 metres are still to go to reach Zuid-Beveland. 'Neeltje Suzanna' only has to bore 210 metres and is expected to arrive in Ellewoutsdjik at the end of January, 2002. Visit www.westerscheldetunnel.nl and www.herrenknecht.com 03/02.
'Sara', the second Herrenknecht Mixshield has completed on 12th February the east bore of the Westerschelde tunnel project following 'Suzanna' which reached its final destination on the west tube three weeks before. See Hall of Fame entry or visit www.herrenknecht.com and www.westerscheldetunnel.nl 09/02.
Her Majesty Queen Beatrix of the Netherlands inaugurated the Dutch longest road traffic tunnel on 14th March. The Zeeuwsch Vlaandren province is cut off from the other parts of the Netherlands by the Westerschelde port entrance to Antwerpen. The new link will provide a faster and more economical route for around 27,000 vehicles a day between Ellewoutsdijk in Zuid-Beveland and Zeeuwsch Vlaanderen near Terneuzen. Central Zeeland and Zeeuwsch Vlaanderen will be permanently linked together. The tunnel is a 6.6 km-long undersea highway tunnel consisting of two tubes, each with two 3.5 m-wide lanes, with 26 cross passages every 250 m. The builders are KMW (Kombinatie Middelplaat Westerschelde), a JV of Philipp Holzmann, Wayss & Freytag, Franki, BAM Infrabouw, Heijmans and Voormolen. 'Sara' and 'Suzanna', two Herrenknecht Mixshields, 11.3 m in diameter, started from an artificial polder at Terneuzen and bored through to 20 m-deep concrete caissons at Ellewoutsdijk. The bulk of the tunnel is running at up to 60 m below sea level, making it the deepest ever to be driven. Both tubes have a concrete lining of 53,000 segments. The €726 million tunnel is open to road users since 15th March. Visit www.westerscheldetunnel.nl and www.herrenknecht.com 12/03.
Netherlands
Sophia - nl/19
Papendrecht
Rail Freight
Part of Betuwe line. Tubecon consortium will start construction in April, 2000 using Herrenknecht 10 m-diameter EPB for 2 x 4 km bores in clays and peaty layers. Overall length of tunnel 8 km to include 2 km-long cut-and-cover sections at each end. Slightly heavier segments than elsewhere on Betuwe line, but 8.65 m inside diameter similar to Botlek to accommodate stacked container traffic. Visit www.herrenknecht.com February 2000.
Herrenknecht advises that its 9.785 m-diameter Mixshield S-150 will be equipped with the revolutionary sonic software probing (SSP) system, a seismic forecasting process that uses sensors installed to the cutting wheel to emit soundwaves into the strata ahead of the machine and receive the reflected signals. The sensors are countersunk into the steel of the spokes and are designed to withstand pressures of up to 6 bar. The data is processed onboard by three high-performance PCs which reproduce a 3-D screen image of the ground up to 40 m ahead. The TBM is being assembled at the launch shaft and boring is scheduled to start in May, 2000. The reception shaft at Hendrik-Ido-Ambacht is still under construction. Contact through www.herrenknecht.com March 2000.
Portugal
Porto - pt/12
Metro
Two lines to be built: north-south between Sto Ovido, Trinidad and Hosp S Joao with 3 km underground, and east-west between Mercado, Trinidad and Campanha, with 2.7 km underground. Concession signed with Metro do Porto and contract placed with Normetro. Civil works by jv of Soares da Costa, Impregilo and Soconstroi. Consultant: Geoconsult E-mail office@gcs.co.at contact F L Jansky. February 1999.
Arge Transmetro will use 8.71 m-diameter Herrenknecht EPB for 5.7 km twin-track extension in mixed loose and solid hard rock comprising 50% to 90% granite, commencing early-2000. Visit www.herrenknecht.com April 2000.
Second Herrenknecht tunnel boring machine ordered by Metro do Porto to link the Salgueiros and Trindade stations under assembly for tunnelling start at summer 2002. Visit www.herrenknecht.com 45/01.
Mott MacDonald and Geodata of Italy have been appointed by Transmetro, a jv of Soares da Costa, Somague and Impregilo, to provide detailed design and construction supervision for all the tunnelling works, which comprise 7 km of bored tunnels lined with reinforced concrete segments for Lines C (2.3 km), S (4 km) and J (700 m). The team will also review and coordinate the design of the civil works with the mechanical, electrical and systems contractors to ensure compatibility and compliance of the works with international best practice. To cope with the varying ground conditions, ranging from massive fresh granite to decomposed and often loose weathered material, two Herrenknecht EPB tunnel boring machines of 8.7 m and 9 m-diameter will be used. Visit www.metro-porto.pt, www.mottmac.com, www.geodata.it or www.herrenknecht.com 09/02.
Open
call for tenders, deadline 21st January, 2008 for construction of the Estádio
do Dragăo-Venda Nova section of the Gondomar line, including a 980 m tunnel.
Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=252962-2007,
OJ S 208, or contact Metro do Porto, Porto, fax +361 225081001. E-mail geral@metro-porto.pt
44/07.
The deadline for submission of tenders for construction of the Estádio do Dragăo-Venda
Nova section of the Gondomar line, including a 980 m tunnel, has been extended
to 4th March, 2008. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=305459-2007,
OJ S 250, or contact Metro do Porto, Porto, fax +361 225081001. E-mail geral@metro-porto.pt
02/08.
The eight candidates to construct the 6.5 km Estádio do Dragăo-Venda Nova section
of the Gondomar line, including a 980 m tunnel, are Mota-Engil, Somague, Soares
da Costa, Monte Adriano and Efacec; Lena, Abrantina and Bento Pedroso; Conduril
and Tecnovia; Isolux Corsán-Corviam, DTS (Domingos da Silva Teixeira) and Alexandre
Barbosa Borges (ABB); Teixeira Duarte, OFM and Thales; Ramalho Rosa, FDO, Gabriel
Couto and FCC; Zagope, Hagen and Siemens; and Edifer and Opway. Construction
will take 21 months for opening in end 2010 or early 2011. 13/08.
Russia
Moscow - ru/18
Lefortovo
Motorway
3.2 km three-lane motorway tunnel to be constructed using 14.2 m-diameter Herrenknecht Mixshield from recently-completed fourth Elbe tunnel in Germany. More from www.herrenknecht.com March 2000.
Ceresola has stripped and refurbished the Elbetunnel concrete segment production
line and installed it for Transstroy Corporation at its Leforto motorway site.
Rings of 13.75 m o.d. erected by Herrenknecht EPB will comprise 8+1 segments
of thickness 700 mm, length 2 m, and with maximum weight 18t. Visit www.ceresola.com
and www.herrenknecht.com
Sept 2000.
Vinci Construction Grands Projets and Russian contractor Transstroy report the breakthrough of the Lefortovo road tunnel in Moscow on 18th February, 2003. The 2,222 m-long tunnel is part of the third orbital peripheral road, east of Moscow, some 4 km from the Kremlin. The JV used a 14.2 m-diameter mixshield TBM, built by Herrenknecht (machine S-164), to drill through fine to coarse sands, clay, and limestone. This is the biggest TBM ever used in urban area. Moscow's famous Military School and river Jausa have been underpassed without settlements. Tunnelling started in November 2001 and lasted 60 weeks with best speed of 32 segmental rings (64 m) in a week. The project will be completed in September. Visit www.herrenknecht.com and www.vinci.com. 09/03.
Saudi
Arabia
Riyadh
- sa/11
Pipelines
Herrenknecht announced that it has delivered a total of
six complete microtunnelling systems for constructing oil and gas pipelines
in Riyadh, Damman and East Saudian. Contact through www.herrenknecht.com
April 2000.
Singapore
Central - sg/11
Deep Sewer
Two large tunnels at depths of 20 m to 50 m. Value $5.2 billion. October 1998.
Concept is to use link sewers to intercept flows from existing gravity sewers upstream of the existing pumping stations and channel them by gravity through deep tunnels to centralised STWs at the south coast and thence to discharge via deep sea outfalls. With up to 45 m water pressure, tunnels will be driven by EPB or slurry TBM with sealed, bolted, grouted precast concrete segmental lining. Final lining will be cast-in-place concrete with corrosion-resistant membrane.
North tunnel from Changi East to Kranji comprises five contracts. T-01 is for 5.9 km of 6.0 m i.d. tunnel with 5 shafts; T-02 is for 7.7 km of 6.0 m with 7 shafts and an odour control facility (OCF); T-03 for 5.2 km of 6.0 m with 10 shafts, 3 ODFs, and a 250 m lateral connector; T-04 is for 7.2 km of 4.3 m i.d. with 9 shafts, 2 ODFs, and an 800 m lateral connector; T-05 is for 12.5 km of 3.6 m i.d. with 11 shafts and one ODF. Eastern two-thirds of the North tunnel is in Old Alluvium, a competent tunnelling medium. Western one-third in granite.
Spur tunnel T-06 connecting Tanglin and Holland Road areas comprises 9.7 km of 3.3 m i.d. tunnel with 8 shafts. Alignment is in fractured sedimentary rock, dense soil and faulted ground requiring shielded TBM with hard and soft rock capability.
Tendering process complete and award imminent. Visit www.gov.sg/gitis/ for full information about tendering contractors and amounts. October 1999.
Design and construct contract for T-02 Bedok tunnel awarded to Penta-Ocean Construction Co. Ltd value S$75.6 bn plus Y1.3 trillion. Design and construct contract for T-05 Kranji tunnel awarded to jv of Philipp Holzmann/Sembcorp value S$139.5 bn. Visit www.hlzm.de January 2000.
Contract T-04 for the Ang Mo Kio tunnel of the Singapore Deep Tunnel Sewerage System has been awarded to Samsung Corporation of 83 Clemenceau Avenue, #09-01 UE Square, Singapore 239920 in the value of $45 million by the Ministry of the Environment, Sewerage Dept, tel +65 731 9591. Source www.gov.sg/gitis/ March 2000.
Remaining contract awards as follows: T-01, Changi tunnel value $47.4 million
to jv of WohHup and Shanghai Tunnel Engineering; T-03 Paya Lebar tunnel value
$40.5 million to jv of Kumagai Gumi and Sembcorp; T-05 Kranji tunnel value $83
million to jv of Sembcorp and Philipp Holzmann. All contracts include shafts.
Contract for T-06 tunnel between Tanglin and Holland Road awaiting award. Visit
www.gov.sg/gitis/
for more information. May 2000.
T-06 contract for 9.6 km x 3.3 m-diameter section between Tanglin and Holland
Road value $60 million awarded to Zueblin Queensway who will use two Herrenknecht
TBMs for completion May, 2004. On the other five contracts the shafts are under
construction at 1.8 m and 3.0 m diameter for access and 10 m to maximum 16 m
for working, with depths of 20 - 50 m. First TBM arrives December, 2000 to start
early 2001. T-01 will use Herrenknecht TBM; T-02 NKK TBM; T-03 Mitsubishi TBM;
T-04 Mitsubishi TBM; and T-05 two Herrenknecht TBMs. Visit www.herrenknecht.com
and look out for www.dtss.gov.sg
under construction. Sept 2000.
Braddle Road in Singapore is reported as having been lowered by a few centimetres. The event occurred shortly after the drilling of a probe hole. Contractors are working in the vicinity on contract T03 of the deep sewer scheme. Their TBM was awaiting an unsealed launch from the adjacent shaft, when sand and water entered the chamber. Local correspondents have noted the spatial juxtapositioning of the three events. Visit www.lta.gov.sg 19/01.
Invitation to tender, deadline 16th September, 2005 for civil engineering for River Valley Link Sewers Contract 2 of the Deep Tunnel Sewerage System. The tender is for the laying of 3 km of reinforced concrete sewer pipes of 1,800 mm and 2,100 mm diameter by pipejacking/microtunnelling method. The contract, when awarded, will have a period of 30 months. Visit www.gebiz.gov.sg, click on Tender Notice and enter PUB000ETT05000138 as ITT No. or contact Public Utilities Board, Singapore, tel. +65 67319567, fax +65 67319699 or e-mail cheng_lay_beng@pub.gov.sg 35/05.
Spain
Guadarrama - es/16
Sierra de Guadarrama
High Speed Railway
Ministry of Development studying submissions from candidates bidding for 30 km tunnel. These are Bechtel (Spain); jv of Dragados, Tecsa and Nesco; jv of Dumez-GTM, AZVI and Ploder; jv of FCC, ACS, Ferrovial and others; and jv of Hochtief, Lain, Obrascon, Huarte and others. Bids invited by September, 1999. Estimated value Pta 350 billion. March 1999.
Contract awarded March 3rd for twin tunnels with cross passages every 300m. Tunnel in granite and gneiss using four closed face TBMs of either single or double telescopic design. April 2000.
GIF has announced contract
awards as follows: lot 1 south tube Madrid side to jv of Necso/Dragados/Tecsa,
value $216.6 million; lot 2 north tube Madrid side to jv of OHL/Hochtief/Sacyr/Guinovart/Comsa,
value $216.5 million; lot 4 north tube Valladolid side to FCC/ACS-Vías y Construcciones/Ferrovial-Agromán,
value $186.8 million. Lot 3 south tube Valladolid side has yet to be awarded.
Construction times vary from 49 months to 57 months, and the exact meeting points
in each tube have not yet been finalised. Tunnelling should commence in Spring,
2001 using four shielded TBMs erecting concrete segmental lining with i.d. 8.5
m. Visit www.necso.es and
www.gif.es June 2000.
Lot 3 for TBM-driven south tube from Valladolid end awarded to consortium of FCC/ACS-Vías y Construcciones/Ferrovial-Agromán value $150 million. Lot 5, value $70 million, for railway construction from portals to Segovia, awarded to Dumez GTM-Azvi. Visit www.gif.es December 2000.
Unity is strength. ACS, Comsa, Dragados, FCC, Ferrovial-Agromán, Hochtief, Necso, OHL, Sacyr, and Tecsa, the ten contractors appointed to drive two 25 km tunnels through granite under the Guadarrama mountain on the high speed railway between Madrid and Valladolid, joined their forces to buy four 8.5 m-diameter TBMs needed for this mammoth job. The coordinated negotiation made it possible to pay Ptas12 billion for the four machines, two Herrenknecht and two Wirth, with a 10% discount, and to cut delivery periods from 19 to 14 months. Both Herrenknecht and Wirth agreed to deliver the TBMs completely mounted, ready for tunnelling. The FCC-Ferrovial-ACS jv will receive two TBMs, one Herrenknecht and one Wirth, to excavate from the northern portals (contracts 3 and 4). The Dragados-Necso-Tecsa jv will use a Wirth TBM to drive the tunnel from one of the south portals (contract 1), while OHL, Sacyr, Comsa and Hochtief will use the second Herrenknecht TBM, from the second south portal (contract 2). The muck will be removed using a conveyor belt. It is expected excavation will start in August, 2002. Engineers estimate the TBMs will bore at an average daily speed of 25 metres or 500 metres a month. Meanwhile, FCC, Ferrovial, and ACS have started the preparatory works from the north portals on the Segovia side. The total cost for both tunnels is €179.6 million. Visit www.herrenknecht.com 50/01.
TBM progress at the Guadarrama tunnels, the greatest civil engineering project ever built in Spain, reached a milestone with a best day of 80 metres. The average daily progress is fourty metres. Benigno Blanco, the infrastructure state secretary, is confident that the 28,377 m-long twin tunnels on the Madrid-Segovia-Valladolid high speed line will be concluded towards the end of 2006 or in early 2007. Tunnelling began in mid-October 2002 in the north drive on the Segovia side. To date, progress has reached 1,800 m on the west tube and 1,500 m on the east tube, both Segovia side. On the south drives (Madrid side), the TBMs drill at the same speed so that about 6 km of tunnel has already been bored out of the 56.7 km. Breakthough is programmed in 30 months. The 9.5 m-diameter tunnels are spaced at a 25 m interval and will be connected by branches every 250 m. Up to 120 tunnellers work in four shifts of six hours. The total investment required is €1.1 billion. Visit www.wirth-europe.com and www.herrenknecht.com 14/03.
Spain
Madrid - es/17
Metro
Following spectacular success with current phase of expansion in which some 35 km of underground lines with 33 stations and 20 km surface line with 4 stations were constructed and commissioned in a four year span, Pta 128,400 million set aside to finance building of metro line to south of Madrid taking in the suburbs of Alcorcon, Leganes, Getafe, Mostoles and Fuenlabrada. 35.2 km tunnels with 29 stations. Construction will not commence until after July, 1999 elections and will then be completed within four years. February 1999.
Extension of Line 1 for 3.2 km to Vallegas with 3 new stations for 2004 opening likely to be next award at $75 million. August 1999.
Herrenknecht 9.38 m TBM will commence 3.5 km drive on line 8 extension from shaft presently under construction at Mar de Cristal station to terminate at shaft to be constructed alongside M-30 ring road. From here conventional tunnelling will be used. Colombia station at approximately halfway position will form interchange with line 9. Visit www.necso.es and www.ferrovial.es for more details. February 2000.
Herrenknecht 9.38 m-diameter EPB under erection in start shaft at Mar De Cristal
in readiness for Line 8 extension drive commencing 21st August. There are currently
37 slurry wall machines at work on this line. Visit www.comadrid.es/cmadrid/metro
July 2000.
9.38 m-diameter NFM EPB Adelantada, working for FCC on Line 10 extension, has completed 939 m of tunnel in 31 days to 20th February, 2001. This is claimed as a world record advance for EPBs. Visit www.fcc.es Also, Lovat 7.4 m-diameter EPB on line 10 built 41 x 1.2 m rings, advancing 49 m in 24 h on 20th February, 2001. Visit www.dragados.com and www.comadrid.es/cmadrid/metro 09/01.
Tunnel linking Mar
de Cristal, Colombia and Nuevos Ministerios on Line 8 reported completed by
jv Necso-ACS-Ferrovial. Direct connection from Paseo de la Castellana to the
Barajas airport to open in March, 2002. 50/01.
Dragados also reported that 7.4 m-diameter Lovat TBM 'Cibeles' has reached Alcorcón
on Line 10 extension to Metrosur circle Line 12. Average speed of 19.6 metres
a day with record daily speed of 51.6 metres and a highest monthly speed of
one kilometre in October, 2001. Cost of €86 million. Construction underway
at stations in Casa de Campo, Colonia Jardín, Cuatro Vientos, Alcalde
Joaquín Vilumbrales, and Puerta del Sur. Opening at spring, 2003. Visit
www.comadrid.es/cmadrid/metro
50/01.
Open call for bids, deadline 2nd February, 2004
for design of the La Castellana extension of the metro. Tender budget: €1.2
million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=214915-2003,
OJ S 241, or contact Mintra, Alcorcón, fax +34 914880598 or 914111724. Visit
www.comadrid.es/012
02/04.
Open call for bids, deadline 2nd February, 2004, for design of Line 1 extension
to Chamartín and Hortaleza. Tender budget: €1.7 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=214916-2003,
OJ S 241, or contact Mintra, Alcorcón, fax +34 914880598 or 914111724. Visit
www.comadrid.es/012
02/04.
Open call for bids, deadline 2nd February, 2004, for design of Line 3 extension
to Villaverde (5.4 km with six stations). Tender budget: €1.8 million. Visit
http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=214919-2003,
OJ S 241, or contact Mintra, Alcorcón, fax +34 914880598 or 914111724. Visit
www.comadrid.es/012
02/04.
Open call for bids, deadline 2nd February, 2004, for design of the new Pinar
del Rey station on Line 8. Tender budget: €516,000. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=214920-2003,
OJ S 241, or contact Mintra, Alcorcón, fax +34 914880598 or 914111724. Visit
www.comadrid.es/012
02/04.
Open call for bids, deadline 2nd February, 2004, for design of Line 11 extension
to Caravanchel Alto (1.6 km with two stations). Tender budget: €830,000. Visit
http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=214926-2003,
OJ S 241, or contact Mintra, Alcorcón, fax +34 914880598 or 914111724. Visit
www.comadrid.es/012
02/04.
Open call for bids, deadline 2nd February, 2004, for design of Line 2 extension
to La Elipa (1.2 km with one station). Tender budget: €700,000. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=214928-2003,
OJ S 241, or contact Mintra, Alcorcón, fax +34 914880598 or 914111724. Visit
www.comadrid.es/012
02/04.
Open call for bids, deadline 2nd February, 2004, for design of the new Bolívar
station on Line 6. Tender budget: €516,000. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=214929-2003,
OJ S 241, or contact Mintra, Alcorcón, fax +34 914880598 or 914111724. Visit
www.comadrid.es/012
02/04.
Open call for bids, deadline 2nd February, 2004, for design of Line 5 extension
to Alameda de Osuna (2 km with two stations). Tender budget: €830,000. Visit
http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=214930-2003,
OJ S 241, or contact Mintra, Alcorcón, fax +34 914880598 or 914111724. Visit
www.comadrid.es/012
02/04.
Open call for bids, deadline 11th February, 2004 for design of Line 4 extension to San Chinarro and Las Tablas (3.8 km with four stations). Tender budget: 1.3 million euros. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=001460-2004, OJ S 2, or contact Mintra, Alcorcón, fax +34 914880598 or 914111724. Visit www.comadrid.es/012 03/04.
Open call for bids,
deadline 15th March, 2004 for quality control and inspections during construction
of the new Aviación Española station on Line 10. Tender values:
EUR106,300 and EUR1.8 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=020317-2004
and http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=020319-2004,
OJ S 23, or contact Mintra, Alcorcón, fax +34 4880598 or 4111724. 07/04.
Open call for bids, deadline 15th March, 2004 for quality control and inspections
during construction of Line 1 extension to Ensache de Vallecas. Tender values:
EUR804,100 and EUR2.3 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=020320-2004,
OJ S 23, and http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=021275-2004,
OJ S 24, or contact Mintra, Alcorcón, fax +34 4880598 or 4111724. 07/04.
Open call for bids, deadline 22nd March, 2004 for construction of the Line 1 extension to Ensanche de Vallecas. Tender budget: EUR91.3 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=025971-2004, OJ S 29, or contact Mintra, Alcorcon, fax +34 916890069. 09/04.
Open call for bids, deadline 12th April, 2004 for construction of Parque Europa station on Line 10 extension to Metrosur. Tender value: EUR13.3 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=035286-2004, OJ S 40, or contact Mintra, Alcorcon, fax +34 916890069. 12/04.
Open call for bids, deadline 15th March, 2004 for quality control and inspections
during construction of the new Aviación Española station on Line 10. Tender
values: EUR106,300 and EUR1.8 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=020317-2004
and http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=020319-2004,
OJ S 23, or contact Mintra, Alcorcón, fax +34 4880598 or 4111724. 07/04.
Open call for bids, deadline 15th March, 2004 for quality control and inspections
during construction of Line 1 extension to Ensanche de Vallecas. Tender values:
EUR804,100 and EUR2.3 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=020320-2004,
OJ S 23, and http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=021275-2004,
OJ S 24, or contact Mintra, Alcorcón, fax +34 4880598 or 4111724. 07/04.
Open call for bids, deadline 22nd March, 2004 for construction of the Line 1
extension to Ensanche de Vallecas. Tender budget: EUR91.3 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=025971-2004,
OJ S 29, or contact Mintra, Alcorcon, fax +34 916890069. 09/04.
Open call for bids, deadline 12th April, 2004 for construction of Parque
Europa station on Line 10 extension to Metrosur. Tender value: EUR13.3 million.
Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=035286-2004,
OJ S 40, or contact Mintra, Alcorcon, fax +34 916890069. 12/04.
Open call for bids, deadline 17th August, 2004, for construction of a Line 1
extension, section Plaza de Castilla-Chamartin interchange. Tender budget: EUR100
million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=117589-2004,
OJ S 137, or contact Mintra, Alcorcon, fax +34 916890069. 31-32/04.
Open call for bids, deadline 13th August, 2004 for construction of extension
to Lines 1 and 4, section Chamartin interchange-Parque de Santa Maria. Tender
budget: EUR170 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=116694-2004,
OJ S 136, or contact Mintra, Alcorcon, fax +34 916890069. 31-32/04.
Open call for bids, deadline 13th August, 2004 for construction of a Line 2
extension to La Elipa. Tender budget: EUR57.4 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=117593-2004,
OJ S 137, or contact Mintra, Alcorcon, fax +34 916890069. 31-32/04.
Open call for bids, deadline 17th August, 2004 for construction of a Line 3
extension to Villaverde, section Legazpi-San Cristobal de los Angeles. Tender
budget: EUR192 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=117590-2004,
OJ S 137, or contact Mintra, Alcorcon, fax +34 916890069. 31-32/04.
Open call for bids, deadline 19th August, 2004 for construction of a Line 5
extension to La Alameda de Osuna. Tender budget: EUR107.4 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=117591-2004,
OJ S 137, or contact Mintra, Alcorcon, fax +34 916890069. 31-32/04.
Open call for bids, deadline 19th August, 2004 for construction of a Line 6
extension. Tender budget: EUR39 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=117587-2004,
OJ S 137, or contact Mintra, Alcorcon, fax +34 916890069. 31-32/04.
Open call for bids, deadline 13th August, 2004 for construction of a Line 7
extension, section 1 Las Musas-M-40. Tender budget: EUR77.7 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=116682-2004,
OJ S 136, or contact Mintra, Alcorcon, fax +34 916890069. 31-32/04.
Open call for bids, deadline 13th August, 2004 for construction of a Line 7
extension, section 2 M-40-Coslada. Tender budget: EUR57.6 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=116679-2004,
OJ S 136, or contact Mintra, Alcorcon, fax +34 916890069. 31-32/04.
Open call for bids, deadline 13th August, 2004 for construction of a Line 7
extension, section 3 Coslada-San Fernado de Henares. Tender budget: EUR181.3
million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=116698-2004,
OJ S 136, or contact Mintra, Alcorcon, fax +34 916890069. 31-32/04.
Open call for bids, deadline 19th August, 2004 for construction of Pinar del
Rey station on Line 8. Tender budget: EUR29.3 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=116696-2004,
OJ S 136, or contact Mintra, Alcorcon, fax +34 916890069. 31-32/04.
Open call for bids, deadline 17th August, 2004 for construction of a Line 11
extension. Tender budget: EUR76.2 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=117592-2004,
OJ S 137, or contact Mintra, Alcorcon, fax +34 916890069. 31-32/04.
Open call for bids, deadline
3rd September, 2004 for inspection and work control during construction of a
line 1 extension, section Plaza de Castilla-Chamartin interchange. Tender budget:
EUR2.2 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=124343-2004,
OJ S 144, or contact Mintra, Alcorcon, fax +34 916890069. The 1,850 m Plaza
de Castilla-Chamartin section includes a single station at a transport interchange.
33-34/04.
Open call for bids, deadline 17th September, 2004 for quality control during
construction of a line 1 extension, section Plaza de Castilla-Chamartin interchange.
Tender budget: EUR725,300. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=127434-2004,
OJ S 147, or contact Mintra, Alcorcon, fax +34 914880598. 33-34/04.
Open call for bids, deadline 1st September, 2004 for inspection and work control
during construction of an extension to Lines 1 and 4, section Chamartin interchange-Parque
de Santa Maria. Tender budget: EUR2.3 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=123383-2004,
OJ S 143, or contact Mintra, Alcorcon, fax +34 916890069. The 4.5 km Chamartin-Santa
Maria section includes four stations. 33-34/04.
Open call for bids, deadline 15th September, 2004 for quality control during
construction of an extension to Lines 1 and 4, section Chamartin interchange-Parque
de Santa Maria. Tender budget: EUR985,000. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=126443-2004,
OJ S 146, or contact Mintra, Alcorcon, fax +34 914880598. 33-34/04.
Open call for bids, deadline 1st September, 2004 for inspection and work control
during construction of a line 2 extension to La Elipa. Tender budget: EUR1.8
million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=123379-2004,
OJ S 143, or contact Mintra, Alcorcon, fax +34 916890069. Line 2 will be extended
by 1.6 km, with one station. 33-34/04.
Open call for bids, deadline 15th September, 2004 for quality control during
construction of a line 2 extension to La Elipa. Tender budget: EUR415,800. Visit
http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=126432-2004,
OJ S 146, or contact Mintra, Alcorcon, fax +34 914880598. 33-34/04.
Open call for bids, deadline 3rd September,, 2004 for inspection and work control
during construction of a line 3 extension to Villaverde, section Legazpi-San
Cristobal de los Angeles. Tender budget: EUR2.4 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=123378-2004,
OJ S 143, or contact Mintra, Alcorcon, fax +34 916890069. Line 3 will be lengthened
from Legazpi to San Cristobal de los Angeles, which will add 6 km and 6 stations.
33-34/04.
Open call for bids, deadline 17th September, 2004 for quality control during
construction of a line 3 extension to Villaverde, section Legazpi-San Cristobal
de los Angeles. Tender budget: EUR1.1 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=126439-2004,
OJ S 146, or contact Mintra, Alcorcon, fax +34 914880598. 33-34/04.
Open call for bids, deadline 6th September, 2004 for inspection and work control
of a line 5 extension to Alameda de Osuna. Tender budget: EUR2 million. Visit
http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=123385-2004,
OJ S 143, or contact Mintra, Alcorcon, fax +34 916890069. Line 5 extension to
Alameda de Osuna will span 2.4 km, with two stations. 33-34/04.
Open call for bids, deadline 20th September, 2004 for quality control during
construction of a line 5 extension to Alameda de Osuna. Tender budget: EUR778,000.
Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=127441-2004,
OJ S 147, or contact Mintra, Alcorcon, fax +34 914880598. 33-34/04.
Open call for bids, deadline 6th September, 2004 for inspection and work control
during construction of the new Arganzuela station on Line 6. Tender budget:
EUR1.9 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=123381-2004,
OJ S 143, or contact Mintra, Alcorcon, fax +34 916890069. This station is on
the circle line 6. 33-34/04.
Open call for bids, deadline 20th September, 2004 for quality control during
construction of the new Arganzuela station on Line 6. Tender budget: EUR283,000.
Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=126426-2004,
OJ S 146, or contact Mintra, Alcorcon, fax +34 914880598. 33-34/04.
Open call for bids, deadline 1st September, 2004 for inspection and work control
during construction of a line 7 extension, section 1 Las Musas-M-40 and section
2 M-40-Coslada. Tender budget: EUR2.3 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=123388-2004,
OJ S 143, or contact Mintra, Alcorcon, fax +34 916890069. Section Las Musas-M-40
is 1.5 km in length with one station. 33-34/04.
Open call for bids, deadline 15th September, 2004 for quality control during
construction of a line 7 extension, section 1 Las Musas-M-40 and section 2 M-40-Coslada.
Tender budget: EUR980,300. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=126445-2004,
OJ S 146, or contact Mintra, Alcorcon, fax +34 914880598. 33-34/04.
Open call for bids, deadline 1st September, 2004 for inspection and work control
during construction of a line 7 extension, section 3 Coslada-San Fernando de
Henares. Tender budget: EUR2.4 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=124354-2004,
OJ S 144, or contact Mintra, Alcorcon, fax +34 916890069. Section Coslada-San
Fernando totals 4.8 km, with five stations. 33-34/04.
Open call for bids, deadline 15th September, 2004 for quality control during
construction of a line 7 extension, section 3 Coslada-San Fernando de Henares.
Tender budget: EUR1 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=126442-2004,
OJ S 146, or contact Mintra, Alcorcon, fax +34 914880598. 33-34/04.
Open call for bids, deadline 6th September, 2004 for inspection and work control
during construction of Pinar del Rey station on Line 8. Tender budget: EUR2
million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=124350-2004,
OJ S 144, or contact Mintra, Alcorcon, fax +34 916890069. This is an intermediate
station on Line 8 to Barajas. 33-34/04.
Open call for bids, deadline 20th September, 2004 for quality control during
construction of Pinar del Rey station on Line 8. Tender budget: EUR212,200.
Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=127436-2004,
OJ S 147, or contact Mintra, Alcorcon, fax +34 914880598. 33-34/04.
Open call for bids, deadline 3rd September, 2004 for inspection and work control
during construction of a line 11 extension to Carabanchel Alto. Tender budget:
EUR2 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=124344-2004,
OJ S 144, or contact Mintra, Alcorcon, fax +34 916890069. The extension spans
2 km with two stations. 33-34/04.
Open call for bids, deadline 17th September, 2004 for quality control during
construction of a line 11 extension to Carabanchel Alto. Tender budget: EUR552,200.
Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=es&docid=126437-2004,
OJ S 146, or contact Mintra, Alcorcon, fax +34 914880598. 33-34/04.
Open call for tenders, deadline 6th October, 2004 for construction of a Line 3 extension to Villaverde, section San Cristobal de los Angeles-Villaverde Alto. This is a 2.1 km section. Tender budget: EUR92.5 million. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=145843-2004, OJ S 169, or contact Mintra, Alcorcon, fax +34 914880098 or 914880598. 37/04.
Open call for bids,
deadline 22nd October, 2004 for quality management during construction of the
infrastructure of Line 3, section San Cristobal de los Angeles-Villaverde Alto.
Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=157392-2004,
OJ S 184, or contact Mintra, Alcorcon, fax +34 914880598. 40/04.
Open call for bids, deadline 21st October 2004 for work inspection and monitoring
during construction of the infrastructure of Line 3, section San Cristobal de
los Angeles-Villaverde Alto. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=157389-2004,
OJ S 184, or contact Mintra, Alcorcon, fax +34 914880598. 40/04.
L. V. Salamanca Ingenieros won a EUR1.8
million contract for work inspection and monitoring during construction of Avenida
de la Aviacion station on Line 10. Euroconsult won the quality management contract
for the same station for EUR106,300. Visit www.lvsalamanca-ingenieros.es
and www.euroconsult.es
43/04.
Ferrovial Agroman will build Line 1 extension to Ensanche de Vallecas for EUR84.8
million. Visit www.ferrovial.com
43/04.
Work inspection and monitoring for Line 1 extension to Ensanche de Vallecas
has been awarded to a JV of Ingenieria Basica de Proyectos and Incoydesa for
EUR2.3 million while Geocisa has been awarded the quality management contract
for EUR720,500. Visit www.incoydesa.com
and www.geocisa.com 43/04.
Begar will build Parque de Europa station on Line 10 for EUR12.2 million. Visit
www.begar.es 43/04.
Ferrovial Agroman
secured a EUR93.1 million contract for construction of a Line 1 extension, section
Plaza de Castilla-Chamartin interchange. Visit www.ferrovial.com
50/04.
Sacyr Vallehermoso clinched a EUR157.5 million deal for construction of extension
to Lines 1 and 4, section Chamartin interchange-Parque de Santa Maria. Visit
www.gruposyv.com 50/04.
OHL will construct an extension to La Elipa on Line 2, for EUR54.8 million.
It is a 1,619 m section for two tracks, featuring a horseshoe-shaped section.
The first 400 m will be built in cut-and-cover, 7.3 m wide x 6.22 m high. Then,
the Madrid tunnelling method, aka Belgian method, will be used for the next
925 m, 9.2 m wide x 7.52 m high (6.35 m high inner diameter after lining), with
timber supports and concrete formwork. Then follows La Elipa station (105 m)
and lastly, the final 80 m will also be built using the Madrid method. Geology
consisting of coarse ground, sandy clays and clayey sands with fines content.
Visit www.ohl.es 50/04.
FCC secured a EUR176.7 million contract for construction of a Line 3 extension
to Villaverde, section Legazpi-San Cristobal de los Angeles. The company has
also been awarded a EUR87 million contract to build the next stretch, San Cristobal
de los Angeles-Villaverde Alto (2.8 km). An EPB shield will be used to drive
a 8.43 m-ID tunnel lined with 32 cm-thick concrete segments. Visit www.fcc.es
50/04.
Ferrovial Agroman has pocketed a EUR94.4 million contract for building Line
5 extension to La Alameda de Osuna. Visit www.ferrovial.com
50/04.
Comsa and Ortiz will build the new Arganzuela station on Line 6, for EUR35.1
million. Visit www.comsa.com
50/04.
Sacyr Vallehermoso will build section 1 Las Musas-M-40 on the east extension
to Line 7. The contract has a value of EUR70 million. This is a 1.1 km section
approximately for two tracks and a cut-and-cover station. Visit www.gruposyv.com
50/04.
ACS Dragados will build the following section on the extension to Line 7, section
2 M-40-Coslada, for EUR50.9 million. It is a twin bored tunnel (2 x 1,986 m,
7.38 m excavated diameter) to be driven with a Lovat TBM owned by Dragados.
No station will be built for the moment but only provisions for two future stations,
one of them being an interchange hub in the residential area where the 2012
Olympic village will be built if Madrid is chosen as host city. Time frame for
construction: 24 months. Visit www.lovat.com
and www.grupoacs.com 50/04.
ACS Dragados has also secured section 3 Coslada-San Fernando de Henares on the
Line 7 extension, for EUR168.4 million. It is a 3,941 m single bore tunnel,
9.38 m outer diameter, and five stations (three in Coslada and two in San Fernando).
A Herrenknecht TBM owned by Dragados will be used. Visit www.herrenknecht.com
and www.grupoacs.com 50/04.
Constructora San Jose and Cimsa will build Pinar del Rey station on Line 8,
for EUR25.8 million and a time frame of 21 months. Visit www.grupo-sanjose.com
50/04.
ACS Dragados won a EUR66.6 million contract for construction of a Line 11 extension
to Carabanchel Alto. It is a 1,286 m single tunnel, 9.38 m OD, to be driven
by means of a NFM Technologies TBM owned by Dragados. Visit www.nfm-technologies.com
and www.grupoacs.com 50/04.
A EUR90,000 geotechnical investigation contract has been awarded by Mintra to Intecsa-Inarsa for core drills in the subsoil, which will study the route of a Line 11 extension from Carabanchel Alto to La Fortuna in Leganes. Technically, the route will start with a 215 m cut-and-cover tunnel in Madrid. Then, a TBM will drive a 3.1 km double-track tunnel until the Leganes district. From that point, the tunnel divides in two single-track branches: one towards the metro station in the area and the other to the rolling stock depot. Visit www.intecsa-inarsa.es 09/05.
Notice of public works concession, deadline 27th March, 2006 for concession contract for the construction and operation of the Line 8 extension from Barajas to the new Madrid airport terminal T-4, inaugurated on 4th February, 2006. Extending Line 8 will require to construct a 2.5 km twin tunnel from the old to the new terminals. The underground station at the new terminal is practically built since it was planned in the project of the new terminal building at Barajas. The two tunnels have to be bored and the internal finishings of the station are pending. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=026272-2006, OJ S 24, or contact Mintra, Alcorcon, fax +34 914880598. E-mail maite.martin@mintramadrid.es 07/06.
The
Madrid regional government has awarded to a JV between FCC and bank Caja Madrid
the 20-year concession contract to build and operate the extension to Madrid
Barajas airport's terminal T-4, for an amount nearing EUR45 million. Visit www.fcc.es
The project consists in extending Line 8, which currently serves terminal T-2,
from the terminus station at Barajas Pueblo. The 2.5 km-long twin bored section
will predominantly be built using a TBM. FCC will use one of the two TBMs employed
to excavate the Line 3 extension to Villaverde. Work starts immediately and
the line will be operational at the end of the first semester of 2007. 19/06.
Open call for tenders,
deadline 8th February, 2007 for extension of Line 11 to La Fortuna. The 3,372
m-long section starts in PAU de Carabanchel to reach La Fortuna. The end of
the line will be connected to the Cuatro Vientos rolling stock depot on Line
10, which is only 500 m distant. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=260749-2006,
OJ S 243, or contact Mintra, Alcorcon, fax +34 914880598. 01-02/07.
Open call for tenders,
deadline 8th August, 2007 for design of the Line 2 extension to Las Rosas. Read
E-News Weekly
29/2007. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=155819-2007,
OJ S 127, or contact Mintra, Alcorcon, fax +34 914880598. 31/07.
Open call for tenders, deadline 8th August, 2007 for design of the Line 3 extension
to El Casar. Read E-News
Weekly 29/2007. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=155818-2007,
OJ S 127, or contact Mintra, Alcorcon, fax +34 914880598. 31/07.
Open call for tenders, deadline 8th August, 2007 for design of the Line 9 extension
to Mirasierra. Read E-News
Weekly 29/2007. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=155808-2007,
OJ S 127, or contact Mintra, Alcorcon, fax +34 914880598. 31/07.
Open invitation
to tender, deadline 19th May, 2008 for design of a new metro line from Chamartin
to Torrejon de Ardoz (infrastructure and fit-out). The new line, 7.5 km in length,
includes three stations (Avenida de la Constitución, Londres and Soto del Henares)
and will run below ground through the industrial parks of San Fernando de Henares
and in Torrejon de Ardoz. The line will start from San Fernando de Henares near
the M-45 then heading north to Torrejon de Ardoz and Soto del Henares. It then
emerges to the surface near the M-50 and connects with the Madrid-Barcelona
rail line and ends at Chamartin station, providing interchange with lines 1
and 10. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=100497-2008,
OJ S 74, or contact Mintra, Madrid, fax +34 914880598. 17/08.
Open invitation to tender, deadline 11th August, 2008 for construction of a
4.75 km extension from La Elipa to Las Rosas on Line 2, with four stations.
The section will be built by TBM. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=157271-2008,
OJ S 118, or contact Mintra, Madrid, fax +34 914880598. E-mail maite.martin@mintramadrid.es
26/08.
A 9.4 m-diameter NFM Technologies EPB tunnel boring machine was officially launched
on 10th June, 2008 by officials, as part of the 2007-2010 transport expansion
programme, to bore the 3.4 km extension of Line 11 from La Peseta to La Fortuna
in Leganes. The machine was last used to build a previous extension of Line
11 from Pan Bendito to La Peseta in Carabanchel. Previously, it completed the
Atocha-Nuevos Ministerios section of the newly opened cross-city railway tunnel
connecting Atocha and Chamartin central stations in Madrid, sections of the
Metrosur Line 12 and a Line 2 extension. Click here.
The construction contract has been awarded to Dragados. Of the 3,400 metres
in tunnel, 25 metres to connect with La Peseta will be mined manually using
Madrid's traditional method. Visit www.nfm-technologies.com
and www.dragados.com 32-33/08.
Spain
Madrid - es/24
Metrosur
TBM
$1.35 billion
39 km-long, 26 station elliptical underground metro line joining five cities to the southwest of Madrid: Alcorcon, Leganes, Getafe, Fuenlabrada, and Mostoles. Additional nine interchange stations with RENFE, the national railway system. Two other cities, Parla and Pinto will be connected into the new metro by commuter trains from Cerca